Outage planning results

Last updated: Thu, 26/05/2022 - 16:40
Your current search

Sites: all sites selected

Outages search found 3509 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
PTS 2309 LFD TRK NNI G 16/03/2023 - 07:30 16/03/2023 - 18:30 D RS 1113214 Approved 07/05/2012 - 15:50
TMU 11BS B2 NNI L 27/03/2023 - 07:30 31/03/2023 - 18:30 C RS 1114241 Approved 07/05/2012 - 15:50
TMU 11BS B1 NNI L 20/03/2023 - 07:30 24/03/2023 - 18:30 C RS 1114240 Approved 07/05/2012 - 15:50
HEP C 11 NNI G 18/08/2022 - 07:30 18/08/2022 - 18:30 D RS 1116895 Approved 07/05/2012 - 15:50
HEP C 12 NNI G 18/08/2022 - 07:30 18/08/2022 - 18:30 D RS 1116896 Approved 07/05/2012 - 15:50
HEP C 11 NNI G 12/06/2023 - 07:00 14/06/2023 - 18:00 C RS 1113515 Approved 07/05/2012 - 15:50
HEP C 11 NNI G 02/08/2022 - 08:30 02/08/2022 - 16:30 D RS 1116379 Approved 07/05/2012 - 15:50
HEP C 12 NNI G 19/06/2023 - 07:00 21/06/2023 - 18:00 C RS 1113517 Approved 07/05/2012 - 15:50
HEP T3 NNI G 19/09/2022 - 07:00 26/09/2022 - 18:00 C RS 1113049 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 22/11/2022 - 07:30 23/11/2022 - 18:30 C RS 1113153 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 10/10/2022 - 07:30 14/10/2022 - 18:30 C OPE 1116362 Cancelled 07/05/2012 - 15:50
MPE CB 252 NNI G 10/10/2022 - 07:30 14/10/2022 - 18:30 C OPE 1116363 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 07/05/2023 - 07:00 09/05/2023 - 18:00 C OPE 1116684 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 07/11/2022 - 07:30 12/11/2022 - 18:30 C OPE 1103181 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 14/11/2022 - 07:30 19/11/2022 - 18:30 C OPE 1103187 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 24/11/2022 - 07:30 24/11/2022 - 18:30 D OPE 1113168 Approved 07/05/2012 - 15:50
EDG 110KV BZ NNI G 13/06/2022 - 08:00 13/06/2022 - 15:00 D RS 1115139 Approved 07/05/2012 - 15:50
EDG 110KV BZ NNI G 22/06/2022 - 08:00 22/06/2022 - 15:00 D RS 1115141 Approved 07/05/2012 - 15:50
EDG 110KV BZ NNI G 16/03/2023 - 07:30 16/03/2023 - 18:30 D RS 1113377 Approved 07/05/2012 - 15:50
ATI CB 148 NNI G 23/01/2023 - 07:00 24/01/2023 - 18:00 C RS 1113244 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 05/12/2022 - 07:30 10/12/2022 - 18:30 C OPE 1103190 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 06/03/2023 - 07:00 08/03/2023 - 18:00 C OPE 1116572 Approved 07/05/2012 - 15:50
OTA 57 47 207 NNI G 17/08/2022 - 07:30 17/08/2022 - 18:30 D RS 1112973 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 18/08/2022 - 08:00 18/08/2022 - 18:00 D RS 1116899 Approved 07/05/2012 - 15:50
PEN 1738 1788 NNI L 19/01/2023 - 07:00 20/01/2023 - 18:00 C RS 1113230 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.