Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
KAW 110BZ NNI G 23/06/2022 - 08:00 23/06/2022 - 15:00 D RS 1115144 Approved 07/05/2012 - 15:50
KAW 110BZ NNI G 13/06/2022 - 08:00 13/06/2022 - 15:00 D RS 1115138 Approved 07/05/2012 - 15:50
ALB SVC 7 HVDC G 20/03/2023 - 07:30 20/03/2023 - 18:30 D RS 1114364 Approved 07/05/2012 - 15:50
ALB SVC 7 HVDC G 18/07/2022 - 07:30 19/07/2022 - 18:30 D RS 1115955 Approved 07/05/2012 - 15:50
ALB C 2 NNI G 03/08/2022 - 07:30 04/08/2022 - 18:30 C RS 1116104 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 06/09/2022 - 08:00 09/09/2022 - 18:00 D RS 1111498 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 20/09/2022 - 07:30 23/09/2022 - 18:00 D RS 1111497 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 02/06/2022 - 08:00 03/06/2022 - 18:00 D RS 1116325 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 16/06/2022 - 08:00 17/06/2022 - 18:00 D RS 1116330 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 04/08/2022 - 08:00 05/08/2022 - 18:00 D RS 1116320 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 30/06/2022 - 08:00 01/07/2022 - 18:00 D RS 1116333 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 06/12/2022 - 09:00 06/12/2022 - 15:00 D SCA 1115827 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 21/11/2022 - 09:00 21/11/2022 - 15:00 D SCA 1115829 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 26/07/2022 - 08:30 26/07/2022 - 16:00 D SCA 1115972 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 16/08/2022 - 08:30 16/08/2022 - 16:00 D SCA 1115976 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 30/08/2022 - 08:30 30/08/2022 - 16:00 D SCA 1115977 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 04/10/2022 - 08:30 04/10/2022 - 16:00 D SCA 1115979 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 13/09/2022 - 07:00 13/09/2022 - 18:00 D RS 1114465 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 27/09/2022 - 08:00 27/09/2022 - 18:00 D RS 1114496 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 20/10/2022 - 08:00 20/10/2022 - 18:00 D RS 1114506 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 13/10/2022 - 08:00 13/10/2022 - 18:00 D RS 1114498 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 03/10/2022 - 07:30 06/10/2022 - 18:30 C RS 1113072 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 21/11/2022 - 07:30 25/11/2022 - 18:30 D RS 1114242 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 16/01/2023 - 07:30 17/01/2023 - 18:30 C OPE 1116568 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 15/08/2022 - 07:00 15/08/2022 - 18:00 D OPE 1112983 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.