Outage planning results

Last updated: Sat, 02/07/2022 - 08:10
Your current search

Sites: all sites selected

Outages search found 3453 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
EDG TRK 2 PROT1 NNI G 21/10/2022 - 07:30 21/10/2022 - 12:00 D RS 1117892 Approved 07/05/2012 - 15:50
EDG TRK 1 PROT2 NNI G 20/10/2022 - 12:30 20/10/2022 - 17:00 D RS 1117734 Approved 07/05/2012 - 15:50
EDG TRK 1 PROT1 NNI G 20/10/2022 - 07:30 20/10/2022 - 12:00 D RS 1117733 Approved 07/05/2012 - 15:50
TGA C 11 NNI G 03/04/2023 - 07:30 04/04/2023 - 18:30 C RS 1113407 Approved 07/05/2012 - 15:50
TMU CB 39 NNI L 19/09/2022 - 07:00 23/09/2022 - 16:00 C RS 1114749 Approved 07/05/2012 - 15:50
TMU CB 37 NNI L 05/09/2022 - 07:00 09/09/2022 - 16:00 C RS 1114747 Approved 07/05/2012 - 15:50
OHW WKM 1 NNI G 15/03/2023 - 07:30 16/03/2023 - 18:30 D RS 1113375 Approved 07/05/2012 - 15:50
OHW WKM 1 NNI G 19/09/2022 - 07:00 23/09/2022 - 17:30 C RS 1101029 Approved 07/05/2012 - 15:50
OHW OTA 2 NNI G 05/12/2022 - 07:30 10/12/2022 - 18:30 C RS 1103175 Approved 07/05/2012 - 15:50
OHW OTA 2 NNI G 14/11/2022 - 07:30 19/11/2022 - 18:30 C RS 1103176 Approved 07/05/2012 - 15:50
HLY OHW 2 NNI G 29/05/2023 - 07:00 31/05/2023 - 18:00 C RS 1113506 Approved 07/05/2012 - 15:50
OHW OTA 1 NNI G 07/11/2022 - 07:30 12/11/2022 - 18:30 C RS 1103174 Approved 07/05/2012 - 15:50
OHW OTA 1 NNI G 12/12/2022 - 07:30 17/12/2022 - 18:30 C RS 1103173 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 28/02/2023 - 07:30 04/03/2023 - 18:30 C RS 1113334 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 24/01/2023 - 07:30 26/01/2023 - 18:30 C RS 1113252 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 17/01/2023 - 07:30 19/01/2023 - 18:30 C RS 1113223 Approved 07/05/2012 - 15:50
HLY OHW 1 NNI G 06/12/2022 - 07:30 07/12/2022 - 18:30 C RS 1113184 Approved 07/05/2012 - 15:50
ROS 110CBF NNI G 01/08/2022 - 07:30 01/08/2022 - 18:30 D RS 1112969 Approved 07/05/2012 - 15:50
ROS 110BZ NNI G 01/08/2022 - 07:30 01/08/2022 - 18:30 D RS 1117386 Approved 07/05/2012 - 15:50
KMO RTU 1 NNI G 04/07/2022 - 07:30 05/07/2022 - 18:30 D RS 1114246 Cancelled 07/05/2012 - 15:50
BOB 110CBF NNI G 06/10/2022 - 08:00 06/10/2022 - 16:00 D RS 1116770 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 11/10/2022 - 07:30 12/10/2022 - 18:00 D RS 1114504 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 12/09/2022 - 07:00 12/09/2022 - 18:00 D RS 1114454 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 08/09/2022 - 07:30 08/09/2022 - 18:00 D RS 1115864 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 15/09/2022 - 07:30 15/09/2022 - 18:00 D RS 1111606 Cancelled 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.