Outage planning results

Last updated: Fri, 10/07/2020 - 18:40
Your current search

Sites: all sites selected

Outages search found 4127 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BRB MDN 1 NNI G 25/01/2021 - 07:30 30/01/2021 - 18:30 C RS 1084797 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 03/08/2020 - 07:00 07/08/2020 - 18:00 C OPE 1082948 Approved 07/05/2012 - 15:49
BOB OTA 1 NNI G 19/04/2021 - 07:30 23/04/2021 - 18:00 C RS 1085422 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 04/03/2021 - 07:30 04/03/2021 - 18:00 D RS 1085421 Approved 07/05/2012 - 15:49
BOB T3 NNI G 01/03/2021 - 07:30 05/03/2021 - 18:30 C RS 1085429 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 19/08/2020 - 07:30 22/08/2020 - 18:30 C RS 1092056 Approved 07/05/2012 - 15:49
BRB MDN 1 NNI G 17/09/2020 - 07:30 17/09/2020 - 18:30 D RS 1091590 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 02/11/2020 - 07:30 06/11/2020 - 18:00 C RS 1085427 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 28/09/2020 - 07:00 30/09/2020 - 18:00 C RS 1092784 Approved 07/05/2012 - 15:49
BRB CB 168 NNI G 19/10/2020 - 07:00 19/10/2020 - 17:00 D RS 1094416 Approved 07/05/2012 - 15:49
BRB T2 NNI G 04/08/2020 - 07:30 05/08/2020 - 18:00 C RS 1085438 Approved 07/05/2012 - 15:49
BRB CB 158 NNI G 12/08/2020 - 07:30 12/08/2020 - 18:30 D RS 1092568 Approved 07/05/2012 - 15:49
BOB FDR 102 NNI L 01/03/2021 - 07:30 04/03/2021 - 18:00 D RS 1088088 Cancelled 07/05/2012 - 15:49
BRB CB 168 NNI G 13/08/2020 - 07:30 13/08/2020 - 18:30 D RS 1092569 Approved 07/05/2012 - 15:49
BRB CB 158 NNI G 02/11/2020 - 07:00 06/11/2020 - 17:00 C RS 1094433 Approved 07/05/2012 - 15:49
BRB CB 168 NNI G 06/11/2020 - 07:00 06/11/2020 - 17:00 D RS 1094442 Approved 07/05/2012 - 15:49
BRB CB 148 NNI G 03/03/2021 - 07:30 03/03/2021 - 18:00 D RS 1085433 Cancelled 07/05/2012 - 15:49
ATI TRK 2 NNI G 02/11/2020 - 07:30 06/11/2020 - 18:00 D RS 1085412 Approved 07/05/2012 - 15:49
BRB CB 158 NNI G 04/03/2021 - 07:30 04/03/2021 - 18:00 D RS 1085434 Cancelled 07/05/2012 - 15:49
ATI TRK 1 NNI G 28/07/2020 - 07:30 31/07/2020 - 18:30 C RS 1093948 Approved 07/05/2012 - 15:49
BRB CB 168 NNI G 16/11/2020 - 07:00 20/11/2020 - 17:00 C RS 1094460 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 01/10/2020 - 07:00 02/10/2020 - 18:00 C RS 1094399 Approved 07/05/2012 - 15:49
BRB CB 168 NNI G 02/11/2020 - 07:00 02/11/2020 - 17:00 D RS 1094435 Approved 07/05/2012 - 15:49
BRB CB 148 NNI G 19/10/2020 - 07:00 19/10/2020 - 17:00 D RS 1094415 Approved 07/05/2012 - 15:49
BRB CB 148 NNI G 09/11/2020 - 07:00 13/11/2020 - 17:00 C RS 1094447 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.