Outage planning results

Last updated: Sun, 31/05/2020 - 10:40
Your current search

Sites: all sites selected

Outages search found 4001 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
NSY AVR T2 SI G 03/06/2020 - 09:00 03/06/2020 - 16:00 D RS 1092590 Approved 18/05/2020 - 11:15
NSY AVR T1 SI G 03/06/2020 - 09:00 03/06/2020 - 16:00 D RS 1092589 Approved 18/05/2020 - 11:13
CLH T1 PROT2 SI G 04/06/2020 - 10:00 04/06/2020 - 12:00 D RS 1092094 Approved 04/05/2020 - 10:51
WPR 33BS SI L 28/07/2020 - 08:30 28/07/2020 - 18:00 D RS 1092802 Approved 17/04/2020 - 13:23
WPR 33BS SI L 10/11/2020 - 07:00 10/11/2020 - 18:00 D RS 1091833 Approved 17/04/2020 - 13:23
WPR 33BS SI L 29/07/2020 - 07:00 30/07/2020 - 18:00 D RS 1091829 Approved 17/04/2020 - 13:23
TMU CB 112 NNI G 06/04/2021 - 07:00 07/04/2021 - 19:00 C RS 1090897 Approved 18/03/2020 - 09:01
TMU CB 62 NNI G 30/03/2021 - 07:00 31/03/2021 - 19:00 C RS 1090896 Approved 18/03/2020 - 08:58
HOR KBY ISL 1 PROT2 SI G 31/07/2020 - 09:00 31/07/2020 - 09:30 D RS 1091059 Approved 17/03/2020 - 13:46
HOR KBY ISL 1 PROT1 SI G 31/07/2020 - 08:30 31/07/2020 - 09:00 D RS 1091058 Approved 17/03/2020 - 13:45
HOR KBY ISL 2 PROT1 SI G 31/07/2020 - 09:30 31/07/2020 - 10:00 D RS 1091060 Approved 17/03/2020 - 13:40
WHU CB 382 NNI G 29/10/2020 - 07:30 29/10/2020 - 18:00 D RS 1091148 Approved 14/02/2020 - 14:43
WHU CB 382 NNI G 23/07/2020 - 09:00 25/07/2020 - 12:00 C RS 1091166 Approved 14/02/2020 - 14:43
WHU CB 2152 NNI G 29/10/2020 - 07:30 12/11/2020 - 12:00 C RS 1091147 Approved 14/02/2020 - 14:37
WHU FDR 2232 NNI L 25/07/2020 - 12:00 06/08/2020 - 17:00 C RS 1091173 Approved 14/02/2020 - 14:21
WHU FDR 2222 NNI L 25/07/2020 - 12:00 13/08/2020 - 17:00 C RS 1091172 Approved 14/02/2020 - 14:20
WHU FDR 2202 NNI L 25/07/2020 - 12:00 10/09/2020 - 17:00 C RS 1091171 Approved 14/02/2020 - 14:18
WHU FDR 2192 NNI L 25/07/2020 - 12:00 03/09/2020 - 17:00 C RS 1091170 Approved 14/02/2020 - 14:13
WHU FDR 2192 NNI L 10/11/2020 - 07:30 10/11/2020 - 16:30 D RS 1091143 Approved 14/02/2020 - 14:13
WHU FDR 2172 NNI L 25/07/2020 - 12:00 20/08/2020 - 17:00 C RS 1091169 Approved 14/02/2020 - 14:12
WHU FDR 2172 NNI L 10/11/2020 - 07:30 10/11/2020 - 16:30 D RS 1091142 Approved 14/02/2020 - 14:12
WHU FDR 2162 NNI L 10/11/2020 - 07:30 10/11/2020 - 16:30 D RS 1091141 Approved 14/02/2020 - 14:00
WHU FDR 2162 NNI L 25/07/2020 - 12:00 27/08/2020 - 17:00 C RS 1091168 Approved 14/02/2020 - 14:00
WHU 33AFD NNI L 29/10/2020 - 07:30 29/10/2020 - 18:00 D RS 1091152 Approved 14/02/2020 - 13:59
WHU 33AFD NNI L 02/11/2020 - 07:30 02/11/2020 - 16:00 D RS 1091157 Approved 14/02/2020 - 13:59
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.