Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BRB HPI 1 PROT1 NNI G 08/12/2020 - 08:00 08/12/2020 - 10:00 D RS 1094499 Approved 15/08/2017 - 11:09
FHL 110CBF SNI G 14/04/2021 - 08:00 14/04/2021 - 17:30 D RS 1095352 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 09/06/2021 - 08:00 09/06/2021 - 17:30 D RS 1095393 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 16/06/2021 - 08:00 16/06/2021 - 12:00 D RS 1095395 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 10/05/2021 - 08:00 10/05/2021 - 17:30 D RS 1095372 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 24/05/2021 - 08:00 24/05/2021 - 17:30 D RS 1095381 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 04/05/2021 - 12:30 04/05/2021 - 17:30 D RS 1095366 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 17/05/2021 - 08:00 17/05/2021 - 12:00 D RS 1095374 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 02/06/2021 - 08:00 02/06/2021 - 12:00 D RS 1095383 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 20/04/2021 - 12:30 20/04/2021 - 17:30 D RS 1095354 Approved 14/07/2017 - 15:37
FHL 110CBF SNI G 27/04/2021 - 08:00 27/04/2021 - 17:30 D RS 1095364 Approved 14/07/2017 - 15:37
EDG 33AFD NNI L 08/03/2021 - 08:00 08/03/2021 - 16:00 D RS 1096749 Approved 27/06/2017 - 13:37
HAM 11AFD NNI L 02/11/2020 - 07:30 02/11/2020 - 16:00 D RS 1095439 Approved 21/06/2017 - 13:43
HAM 11AFD NNI L 16/11/2020 - 07:30 16/11/2020 - 16:00 D RS 1095437 Approved 21/06/2017 - 13:43
HAM 11AFD NNI L 09/11/2020 - 07:30 09/11/2020 - 18:00 D RS 1095440 Approved 21/06/2017 - 13:43
HAM 11AFD NNI L 23/11/2020 - 07:30 23/11/2020 - 18:30 D RS 1095438 Approved 21/06/2017 - 13:43
TAK FDR 2352 NNI L 27/10/2020 - 07:30 12/11/2020 - 18:00 C RS 1096924 Approved 15/06/2017 - 10:02
TAK FDR 2242 NNI L 16/11/2020 - 07:00 02/12/2020 - 17:00 C RS 1097212 Approved 15/06/2017 - 10:01
BRY C 7A SI G 30/11/2020 - 07:30 04/12/2020 - 18:30 C RS 1087081 Approved 14/06/2017 - 14:19
BRY C 7A SI G 15/08/2020 - 11:30 27/11/2020 - 18:00 C RS 1095749 Released 14/06/2017 - 14:19
INV T1 SI G 01/03/2021 - 07:30 05/03/2021 - 18:30 C RS 1095903 Approved 24/05/2017 - 08:30
TNG 11BZ K SNI L 09/02/2021 - 07:30 09/02/2021 - 17:30 D RS 1086497 Approved 20/01/2017 - 13:58
TNG 11BZ L SNI L 10/02/2021 - 07:30 10/02/2021 - 17:30 D RS 1086498 Approved 20/01/2017 - 13:56
KPU FDR 1042 NNI L 11/11/2020 - 10:00 11/11/2020 - 14:00 D RS 1092281 Approved 19/10/2016 - 10:24
GOR 110BZ SI G 09/02/2021 - 07:30 10/02/2021 - 18:30 D RS 1087119 Approved 20/09/2016 - 08:41
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.