Outage planning results

Last updated: Mon, 26/10/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 3556 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TKR CB 138 SNI G 01/02/2021 - 07:00 02/02/2021 - 18:30 D RS 1086479 Approved 11/05/2015 - 08:22
ALB T4 NNI G 07/12/2020 - 07:30 24/12/2020 - 18:30 C RS 1085393 Approved 07/05/2012 - 15:49
ALB T6 NNI G 27/10/2020 - 07:30 13/11/2020 - 18:30 C RS 1085394 Approved 07/05/2012 - 15:49
ARI HAM 1 NNI G 28/11/2020 - 07:00 28/11/2020 - 18:00 D OPE 1094472 Approved 07/05/2012 - 15:49
SFD 110BZ A PROT1 SNI G 09/02/2021 - 08:00 09/02/2021 - 10:00 D RS 1093844 Approved 08/01/2019 - 08:14
ASY CB 2742 SI G 23/11/2020 - 07:30 27/11/2020 - 18:30 C CLO 1087563 Approved 15/05/2015 - 13:18
SFD 110BZ A PROT1 SNI G 13/02/2021 - 07:30 13/02/2021 - 12:00 D RS 1093852 Approved 08/01/2019 - 08:14
KIN 307 317 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096863 Approved 05/03/2020 - 15:17
SFD 110BZ A PROT2 SNI G 13/02/2021 - 12:30 13/02/2021 - 17:00 D RS 1093854 Approved 08/01/2019 - 08:50
BPE PRM HAY 2 SNI G 21/01/2021 - 06:00 23/01/2021 - 18:30 C RS 1086576 Approved 16/10/2014 - 10:32
SFD 110BZ A PROT2 SNI G 09/02/2021 - 10:00 09/02/2021 - 12:00 D RS 1093847 Approved 08/01/2019 - 08:50
HWB CB 2548 SI G 08/03/2021 - 08:00 09/03/2021 - 17:00 C RS 1093740 Cancelled 16/06/2020 - 11:09
SFD 110BZ B PROT2 SNI G 09/02/2021 - 10:00 09/02/2021 - 12:00 D RS 1093848 Approved 08/01/2019 - 09:09
PNI TKR 1 SNI G 26/01/2021 - 07:00 27/01/2021 - 18:30 D RS 1086405 Approved 24/10/2014 - 11:49
SFD 110BZ B PROT2 SNI G 13/02/2021 - 12:30 13/02/2021 - 17:00 D RS 1093855 Approved 08/01/2019 - 09:09
WGN WVY 1 PROT1 SNI G 19/11/2020 - 09:00 19/11/2020 - 17:00 D RS 1095877 Approved 18/06/2020 - 15:54
SFD 110BZ B PROT1 SNI G 13/02/2021 - 07:30 13/02/2021 - 12:00 D RS 1093853 Approved 08/01/2019 - 09:38
WVY CB 112 PROT1 SNI G 02/12/2020 - 09:00 02/12/2020 - 13:00 D RS 1095835 Approved 15/07/2020 - 16:54
SFD 110BZ B PROT1 SNI G 09/02/2021 - 08:00 09/02/2021 - 10:00 D RS 1093845 Approved 08/01/2019 - 09:38
SFD 82 112 127 SNI G 01/02/2021 - 07:30 01/02/2021 - 18:00 D RS 1094856 Approved 16/07/2020 - 15:48
SFD 110CBF PROT1 SNI G 09/02/2021 - 08:00 09/02/2021 - 10:00 D RS 1093846 Approved 08/01/2019 - 09:40
WHU CB 2152 NNI G 09/11/2020 - 08:00 23/11/2020 - 12:00 C RS 1091147 Approved 14/02/2020 - 14:37
WHU CB 382 NNI G 09/11/2020 - 08:00 09/11/2020 - 18:00 D RS 1091148 Approved 14/02/2020 - 14:43
SFD 110CBF PROT1 SNI G 13/02/2021 - 07:30 13/02/2021 - 12:00 D RS 1093856 Approved 08/01/2019 - 09:40
BOB HAM 2 NNI G 18/10/2021 - 08:00 20/10/2021 - 18:00 C OPE 1078227 Cancelled 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.