Outage planning results

Last updated: Sat, 08/05/2021 - 19:40
Your current search

Sites: all sites selected

Outages search found 3552 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HOR RTU 1 SI G 21/06/2021 - 09:00 21/06/2021 - 11:00 D RS 1102657 Approved 07/05/2012 - 15:51
TAK T5 NNI G 02/08/2021 - 08:00 07/08/2021 - 18:30 D RS 1100151 Approved 07/05/2012 - 15:49
KIN TRK 2 NNI G 27/11/2021 - 07:30 28/11/2021 - 18:30 D RS 1100627 Approved 07/05/2012 - 15:49
TAK T5 NNI G 28/05/2021 - 07:30 28/05/2021 - 18:30 D RS 1098143 Approved 07/05/2012 - 15:49
KOE MPE 1 NNI G 29/11/2021 - 07:00 30/11/2021 - 18:00 D RS 1100648 Approved 07/05/2012 - 15:49
TAK T8 NNI G 23/08/2021 - 08:00 28/08/2021 - 18:30 D RS 1100235 Approved 07/05/2012 - 15:49
HEP T1 NNI G 16/06/2021 - 09:00 16/06/2021 - 17:00 D RS 1102620 Approved 07/05/2012 - 15:49
KOE MPE 1 NNI G 26/05/2021 - 07:30 26/05/2021 - 17:00 D RS 1104060 Approved 07/05/2012 - 15:49
TAK T8 NNI G 02/11/2022 - 08:00 02/11/2022 - 16:00 D RS 1097042 Approved 07/05/2012 - 15:49
HIN FDR 242 NNI L 13/06/2021 - 07:30 13/06/2021 - 18:00 D RS 1104511 Approved 07/05/2012 - 15:49
WIR T2 NNI G 25/06/2021 - 12:30 25/06/2021 - 16:00 D RS 1103793 Approved 07/05/2012 - 15:49
TAK T8 NNI G 23/03/2022 - 07:00 25/03/2022 - 18:00 D RS 1101202 Approved 07/05/2012 - 15:49
TGA T2 NNI G 17/08/2021 - 07:30 17/08/2021 - 18:30 D RS 1100226 Approved 07/05/2012 - 15:49
TGA T3 NNI G 17/09/2021 - 07:30 17/09/2021 - 18:30 D RS 1100312 Approved 07/05/2012 - 15:49
TGA T4 NNI G 17/08/2021 - 07:30 17/08/2021 - 18:30 D OPE 1101917 Approved 07/05/2012 - 15:49
TMU FDR 23 NNI L 01/06/2021 - 07:30 04/06/2021 - 18:00 D RS 1085896 Approved 07/05/2012 - 15:49
KPO TMU 1 NNI G 24/08/2021 - 08:00 26/08/2021 - 18:30 D OPE 1097669 Cancelled 07/05/2012 - 15:49
KPO TMU 1 NNI G 11/12/2021 - 07:00 13/12/2021 - 18:00 D OPE 1102270 Approved 07/05/2012 - 15:49
HAM T8 NNI G 23/05/2021 - 07:00 23/05/2021 - 16:00 D RS 1104402 Approved 07/05/2012 - 15:49
TMU T2 NNI G 02/07/2021 - 10:00 02/07/2021 - 18:00 D RS 1103794 Approved 07/05/2012 - 15:49
TMU T2 NNI G 06/07/2021 - 07:30 06/07/2021 - 12:30 D RS 1103081 Approved 07/05/2012 - 15:49
TMU T2 NNI G 05/07/2021 - 10:00 05/07/2021 - 18:00 D RS 1103796 Approved 07/05/2012 - 15:49
KPO TMU 1 NNI G 22/02/2022 - 07:30 25/02/2022 - 18:30 D OPE 1101035 Approved 07/05/2012 - 15:49
KPO TMU 1 NNI G 08/02/2022 - 07:30 11/02/2022 - 18:30 D OPE 1100920 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 17/11/2021 - 08:00 17/11/2021 - 18:30 D RS 1097699 Cancelled 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.