Outage planning results

Last updated: Sat, 23/01/2021 - 19:40
Your current search

Sites: all sites selected

Outages search found 2862 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
GLN 220BS A NNI G 21/04/2021 - 07:00 21/04/2021 - 18:00 D RS 1085484 Approved 07/05/2012 - 15:49
GLN 220BS B NNI G 06/04/2021 - 12:00 06/04/2021 - 18:00 D RS 1085497 Approved 07/05/2012 - 15:49
GLN 220BS B NNI G 08/04/2021 - 07:00 08/04/2021 - 18:00 D RS 1085498 Approved 07/05/2012 - 15:49
GLN 220BS B NNI G 13/04/2021 - 07:00 13/04/2021 - 18:00 D RS 1085499 Approved 07/05/2012 - 15:49
GLN 220BS B NNI G 19/04/2021 - 12:00 19/04/2021 - 18:00 D RS 1085500 Approved 07/05/2012 - 15:49
GLN 220BS B NNI G 20/04/2021 - 12:00 20/04/2021 - 18:00 D RS 1085501 Approved 07/05/2012 - 15:49
GLN 220BS B NNI G 22/04/2021 - 07:00 22/04/2021 - 18:00 D RS 1085502 Approved 07/05/2012 - 15:49
GLN T4 NNI G 06/04/2021 - 07:00 06/04/2021 - 18:00 D RS 1085505 Approved 07/05/2012 - 15:49
GLN T5 NNI G 12/04/2021 - 07:00 16/04/2021 - 18:00 C RS 1085509 Approved 07/05/2012 - 15:49
GLN T6 NNI G 20/04/2021 - 07:00 20/04/2021 - 18:00 D RS 1085512 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 24/02/2021 - 07:00 24/02/2021 - 18:00 D RS 1085513 Approved 07/05/2012 - 15:49
HAM 110CBF NNI G 24/02/2021 - 07:00 24/02/2021 - 18:00 D RS 1085514 Approved 07/05/2012 - 15:49
HAM 117 157 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085515 Approved 07/05/2012 - 15:50
HAM 127 224 NNI G 08/03/2021 - 07:00 12/03/2021 - 18:00 D RS 1085516 Cancelled 07/05/2012 - 15:50
HAM 427 467 487 NNI G 21/04/2021 - 07:30 21/04/2021 - 18:00 D RS 1085520 Approved 07/05/2012 - 15:49
HAM CB 118 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085521 Approved 07/05/2012 - 15:50
HAM CB 118 NNI G 08/03/2021 - 07:00 12/03/2021 - 18:00 D RS 1085522 Cancelled 07/05/2012 - 15:50
HAM KPO 1 NNI G 08/03/2021 - 07:00 12/03/2021 - 18:00 D RS 1085524 Cancelled 07/05/2012 - 15:49
HAM KPO 2 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085525 Approved 07/05/2012 - 15:49
HAM OHW 1 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085526 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 06/03/2021 - 07:00 07/03/2021 - 19:00 D RS 1085527 Approved 07/05/2012 - 15:50
HAM PAO WHU 1 NNI G 10/05/2021 - 07:00 14/05/2021 - 19:00 C RS 1085528 Approved 07/05/2012 - 15:49
HAM PAO WHU 2 NNI G 23/02/2021 - 07:30 25/02/2021 - 19:30 D RS 1085529 Approved 07/05/2012 - 15:49
HAM T1 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085531 Approved 07/05/2012 - 15:49
HAM T2 NNI G 08/03/2021 - 07:00 12/03/2021 - 18:00 D RS 1085533 Cancelled 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.