Outage planning results

Last updated: Fri, 27/05/2022 - 18:40
Your current search

Sites: all sites selected

Outages search found 3469 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
KWA T3 SNI G 20/03/2023 - 07:00 21/03/2023 - 18:30 D RS 1112643 Approved 07/05/2012 - 15:53
PTS 1742 GFD HAY SNI G 18/05/2023 - 08:00 18/05/2023 - 18:30 D RS 1112747 Approved 07/05/2012 - 15:53
PTS 1744 GFD HAY SNI G 18/05/2023 - 08:00 18/05/2023 - 18:30 D RS 1112748 Approved 07/05/2012 - 15:53
BPE WDV 1 PROT1 SNI G 14/06/2022 - 07:30 14/06/2022 - 11:30 D RS 1115940 Approved 07/05/2012 - 15:53
BPE WDV 1 PROT2 SNI G 14/06/2022 - 12:00 14/06/2022 - 16:00 D RS 1115941 Approved 07/05/2012 - 15:53
BPE WDV 2 PROT1 SNI G 13/06/2022 - 07:30 13/06/2022 - 11:30 D RS 1115942 Approved 07/05/2012 - 15:53
BPE WDV 2 PROT2 SNI G 13/06/2022 - 12:00 13/06/2022 - 16:00 D RS 1115943 Approved 07/05/2012 - 15:53
KWA CB 14 SNI G 07/06/2022 - 07:00 08/06/2022 - 17:00 C RS 1110447 Approved 07/05/2012 - 15:53
KWA CB 14 SNI G 14/04/2023 - 07:30 14/04/2023 - 18:30 D RS 1112806 Approved 07/05/2012 - 15:53
KWA CB 8 SNI G 12/04/2023 - 07:30 13/04/2023 - 18:30 D RS 1112803 Approved 07/05/2012 - 15:53
KWA CB 8 SNI G 09/06/2022 - 07:00 10/06/2022 - 17:00 C RS 1110450 Approved 07/05/2012 - 15:53
HAY 27 VT47 SNI G 02/11/2022 - 07:30 03/11/2022 - 18:30 C RS 1112598 Approved 07/05/2012 - 15:53
RDF CB 78 SNI G 08/02/2023 - 07:30 08/02/2023 - 18:30 D RS 1112770 Approved 07/05/2012 - 15:53
RDF CB 78 SNI G 31/05/2022 - 07:30 31/05/2022 - 18:00 D RS 1114099 Approved 07/05/2012 - 15:53
WDV T2 SNI G 07/06/2023 - 07:30 07/06/2023 - 18:30 D RS 1112827 Approved 07/05/2012 - 15:53
RDF 54 94 97 SNI G 20/02/2023 - 07:30 20/02/2023 - 18:30 D RS 1112762 Approved 07/05/2012 - 15:53
RDF 54 94 97 SNI G 31/05/2022 - 07:30 31/05/2022 - 18:00 D RS 1114093 Approved 07/05/2012 - 15:53
RDF 87 187 SNI G 08/02/2023 - 07:30 08/02/2023 - 18:30 D RS 1112766 Approved 07/05/2012 - 15:53
WIL 220CBF SNI G 01/06/2022 - 07:30 01/06/2022 - 17:00 D RS 1114485 Approved 07/05/2012 - 15:53
WIL 220CBF SNI G 18/07/2022 - 07:30 18/07/2022 - 18:30 D RS 1112877 Approved 07/05/2012 - 15:53
NAP 220BZ SNI G 28/11/2022 - 07:00 28/11/2022 - 18:30 D RS 1112505 Approved 07/05/2012 - 15:53
WDV 11BZ SNI L 17/02/2023 - 07:30 17/02/2023 - 18:30 D RS 1112809 Approved 07/05/2012 - 15:53
RDF 110BZ SNI G 11/05/2023 - 07:30 11/05/2023 - 18:30 D RS 1112754 Approved 07/05/2012 - 15:53
WDV 11CBF SNI L 17/02/2023 - 07:30 17/02/2023 - 18:30 D RS 1112810 Approved 07/05/2012 - 15:53
WVY T1 SNI G 27/11/2022 - 09:00 27/11/2022 - 18:00 D RS 1112504 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.