Outage planning results

Last updated: Mon, 18/10/2021 - 17:10
Your current search

Sites: all sites selected

Outages search found 3669 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB C 11 NNI G 27/10/2021 - 08:00 27/10/2021 - 17:00 D RS 1097009 Approved 07/05/2012 - 15:50
ROT TRK 2 PROT2 NNI G 11/02/2022 - 14:00 11/02/2022 - 18:00 D RS 1106477 Approved 07/05/2012 - 15:50
ROT WHE 1 PROT2 NNI G 11/02/2022 - 09:00 11/02/2022 - 13:00 D RS 1106476 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 28/10/2021 - 08:00 28/10/2021 - 17:00 D RS 1097017 Approved 07/05/2012 - 15:50
MPE RTU 2 NNI G 19/10/2021 - 07:30 19/10/2021 - 18:30 D RS 1103600 Cancelled 07/05/2012 - 15:50
HEP C 13 NNI G 19/04/2022 - 07:30 02/05/2022 - 18:30 C RS 1103135 Approved 07/05/2012 - 15:50
HLY OHW 1 NNI G 15/11/2021 - 08:00 18/11/2021 - 18:30 C RS 1100586 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 08/02/2022 - 07:00 12/02/2022 - 19:00 C RS 1100919 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 11/12/2021 - 07:00 13/12/2021 - 18:00 D RS 1100723 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 18/10/2021 - 08:00 20/10/2021 - 18:00 C RS 1078221 Cancelled 07/05/2012 - 15:50
HAM OHW 1 NNI G 18/10/2021 - 07:00 22/10/2021 - 19:00 C RS 1102363 Cancelled 07/05/2012 - 15:50
HAM OHW 1 NNI G 29/11/2021 - 08:00 03/12/2021 - 18:00 C RS 1078234 Cancelled 07/05/2012 - 15:50
HAM OHW 1 NNI G 22/02/2022 - 07:30 25/02/2022 - 18:30 D RS 1101034 Cancelled 07/05/2012 - 15:50
OHW OTA 1 NNI G 11/04/2022 - 07:00 14/04/2022 - 18:30 C RS 1107771 Approved 07/05/2012 - 15:50
OHW OTA 1 NNI G 26/04/2022 - 07:30 29/04/2022 - 18:30 C RS 1109460 Approved 07/05/2012 - 15:50
OHW OTA 1 NNI G 28/03/2022 - 07:00 02/04/2022 - 18:00 C RS 1107770 Approved 07/05/2012 - 15:50
OHW OTA 1 NNI G 24/01/2022 - 07:00 24/01/2022 - 18:30 D RS 1106790 Approved 07/05/2012 - 15:50
OHW OTA 1 NNI G 14/12/2021 - 07:00 18/12/2021 - 18:00 C RS 1100738 Approved 07/05/2012 - 15:50
HLY OHW 2 NNI G 18/01/2022 - 07:00 21/01/2022 - 18:00 C RS 1100823 Approved 07/05/2012 - 15:50
HLY OHW 2 NNI G 22/11/2021 - 08:00 27/11/2021 - 18:30 C RS 1100622 Approved 07/05/2012 - 15:50
OHW OTA 2 NNI G 25/01/2022 - 07:00 28/01/2022 - 18:30 C RS 1100857 Approved 07/05/2012 - 15:50
OHW OTA 2 NNI G 04/04/2022 - 07:30 09/04/2022 - 18:30 C RS 1109461 Approved 07/05/2012 - 15:50
OHW OTA 2 NNI G 19/04/2022 - 07:30 23/04/2022 - 18:30 C RS 1109462 Approved 07/05/2012 - 15:50
OHW WKM 1 NNI G 21/02/2022 - 07:30 26/02/2022 - 18:30 D RS 1101029 Approved 07/05/2012 - 15:50
OHW WKM 1 NNI G 22/11/2021 - 07:00 25/11/2021 - 17:30 C RS 1102369 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.