Outage planning results

Last updated: Wed, 28/07/2021 - 15:40
Your current search

Sites: all sites selected

Outages search found 3672 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
EDG OWH 2 NNI G 15/02/2022 - 07:00 15/02/2022 - 18:30 D RS 1106698 Approved 07/05/2012 - 15:49
OWH 110BZ NNI G 16/02/2022 - 08:00 16/02/2022 - 17:00 D RS 1106699 Approved 29/05/2017 - 11:25
OWH 110CBF NNI G 16/02/2022 - 08:00 16/02/2022 - 17:00 D RS 1106700 Approved 29/05/2017 - 11:26
OWH 110BZ NNI G 23/02/2022 - 08:00 23/02/2022 - 17:30 D RS 1106701 Approved 29/05/2017 - 11:25
OWH 110CBF NNI G 23/02/2022 - 08:00 23/02/2022 - 17:30 D RS 1106702 Approved 29/05/2017 - 11:26
OWH 82 92 107 NNI G 24/02/2022 - 07:00 24/02/2022 - 18:00 D RS 1106703 Approved 07/05/2012 - 15:50
EDG OWH 2 NNI G 21/02/2022 - 07:30 24/02/2022 - 18:00 C RS 1106704 Approved 07/05/2012 - 15:49
OWH T2 NNI G 07/03/2022 - 07:00 17/03/2022 - 17:00 C RS 1106705 Approved 07/05/2012 - 15:49
OWH 110BZ NNI G 07/03/2022 - 08:00 07/03/2022 - 17:00 D RS 1106706 Approved 29/05/2017 - 11:25
OWH 110CBF NNI G 07/03/2022 - 08:00 07/03/2022 - 17:00 D RS 1106707 Approved 29/05/2017 - 11:26
OWH 110BZ NNI G 16/03/2022 - 08:00 16/03/2022 - 17:30 D RS 1106708 Approved 29/05/2017 - 11:25
OWH 110CBF NNI G 16/03/2022 - 08:00 16/03/2022 - 17:30 D RS 1106709 Approved 29/05/2017 - 11:26
CML T8 SI G 18/08/2021 - 07:30 18/08/2021 - 18:00 D OPE 1106711 Approved 07/05/2012 - 15:52
CST JRD SFD 1 PROT2 SNI G 09/10/2021 - 10:00 09/10/2021 - 14:00 D RS 1106720 Approved 15/01/2020 - 13:22
EDG KAW 2 NNI G 08/02/2022 - 07:30 10/02/2022 - 17:30 C RS 1106721 Approved 07/05/2012 - 15:49
CST SFD 3 PROT2 SNI G 10/10/2021 - 10:00 10/10/2021 - 14:00 D RS 1106722 Approved 15/01/2020 - 13:24
CST JRD SFD 1 PROT2 SNI G 10/10/2021 - 14:00 10/10/2021 - 18:00 D RS 1106723 Approved 15/01/2020 - 13:22
CST JRD SFD 1 PROT2 SNI G 11/10/2021 - 10:00 11/10/2021 - 13:00 D RS 1106724 Approved 15/01/2020 - 13:22
CST SFD 3 PROT2 SNI G 11/10/2021 - 13:00 11/10/2021 - 16:00 D RS 1106725 Approved 15/01/2020 - 13:24
OWH RTU 1 NNI G 05/11/2021 - 07:30 05/11/2021 - 17:00 D SCA 1106727 Approved 07/05/2012 - 15:49
OWH RTU 1 NNI G 12/11/2021 - 07:30 12/11/2021 - 17:00 D SCA 1106728 Approved 07/05/2012 - 15:49
OWH RTU 1 NNI G 19/11/2021 - 07:30 19/11/2021 - 17:00 D SCA 1106729 Approved 07/05/2012 - 15:49
PNI TKR 1 SNI G 06/12/2021 - 07:30 07/12/2021 - 18:00 D RS 1106730 Approved 24/10/2014 - 11:49
PNI T1 SNI G 06/12/2021 - 07:30 07/12/2021 - 18:00 D RS 1106731 Approved 07/05/2012 - 15:52
OWH RTU 1 NNI G 26/11/2021 - 07:30 26/11/2021 - 17:00 D SCA 1106732 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.