Outage planning results

Last updated: Fri, 27/05/2022 - 11:40
Your current search

Sites: all sites selected

Outages search found 3464 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WIL FDR 2232 SNI L 02/03/2023 - 18:30 03/03/2023 - 18:30 D RS 1112894 Approved 10/02/2014 - 13:27
BOB FDR 272 NNI L 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097028 Approved 07/05/2012 - 15:49
WIL FDR 2242 SNI L 02/03/2023 - 18:30 03/03/2023 - 18:30 D RS 1112895 Approved 10/02/2014 - 13:30
BOB FDR 272 NNI L 13/09/2022 - 07:00 13/09/2022 - 18:00 D RS 1114460 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 23/09/2022 - 07:00 23/09/2022 - 18:00 D RS 1114561 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 11/10/2022 - 07:00 11/10/2022 - 18:00 D RS 1114501 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 26/10/2022 - 07:00 26/10/2022 - 18:00 D RS 1114563 Approved 07/05/2012 - 15:49
BOB FDR 212 NNI L 02/11/2022 - 07:00 02/11/2022 - 18:00 D RS 1113106 Approved 07/05/2012 - 15:49
WIL FDR 2252 SNI L 02/03/2023 - 18:30 03/03/2023 - 18:30 D RS 1112896 Approved 10/02/2014 - 13:32
WIL FDR 2252 SNI L 11/07/2022 - 07:00 13/07/2022 - 18:30 C RS 1116878 Approved 10/02/2014 - 13:32
TMK FDR 1222 SI L 14/07/2022 - 08:30 15/07/2022 - 08:00 C RS 1116794 Approved 07/05/2012 - 15:51
TMK FDR 1202 SI L 12/07/2022 - 08:30 13/07/2022 - 08:00 C RS 1116792 Approved 07/05/2012 - 15:51
TMK CB 1248 SI L 20/07/2022 - 12:00 20/07/2022 - 17:00 D RS 1113551 Approved 07/05/2012 - 15:51
TMK CB 1248 SI L 18/07/2022 - 08:30 19/07/2022 - 08:00 C RS 1116795 Approved 07/05/2012 - 15:51
MCH 11BS SI L 10/07/2022 - 07:30 10/07/2022 - 17:30 D RS 1113621 Approved 07/05/2012 - 15:51
MCH 11BS SI L 17/07/2022 - 07:30 17/07/2022 - 17:30 D RS 1113606 Approved 07/05/2012 - 15:51
TMK FDR 1262 SI L 15/07/2022 - 08:30 18/07/2022 - 08:00 C RS 1116796 Approved 07/05/2012 - 15:51
MCH CB 32 SI L 10/07/2022 - 07:30 10/07/2022 - 17:30 D RS 1113622 Approved 07/05/2012 - 15:51
MCH CB 32 SI L 17/07/2022 - 07:30 17/07/2022 - 17:30 D RS 1113607 Approved 07/05/2012 - 15:51
PNI 237 294 SNI L 12/01/2023 - 07:30 12/01/2023 - 18:30 D RS 1112695 Approved 07/05/2012 - 15:53
OWH FDR 10 NNI L 18/08/2022 - 07:30 28/09/2022 - 17:00 C RS 1110185 Approved 07/05/2012 - 15:49
OWH FDR 11 NNI L 30/08/2022 - 07:30 28/09/2022 - 17:00 C RS 1110188 Approved 07/05/2012 - 15:49
OWH FDR 13 NNI L 09/08/2022 - 07:30 28/09/2022 - 17:00 C RS 1110183 Approved 07/05/2012 - 15:49
CBG 11BS A NNI L 03/10/2022 - 07:30 06/10/2022 - 18:30 C RS 1115242 Approved 20/11/2013 - 14:46
PNI 214 257 SNI L 11/01/2023 - 07:30 11/01/2023 - 18:30 D RS 1112694 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.