Outage planning results

Last updated: Tue, 19/10/2021 - 12:10
Your current search

Sites: all sites selected

Outages search found 3635 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB HAM 2 NNI G 22/02/2022 - 07:30 25/02/2022 - 18:30 D OPE 1101036 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 21/10/2021 - 18:31 22/10/2021 - 19:00 C OPE 1108813 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 13/11/2021 - 07:30 14/11/2021 - 16:30 D RS 1097025 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 05/09/2022 - 07:30 05/09/2022 - 18:30 D RS 1097018 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 25/10/2021 - 08:00 27/10/2021 - 18:00 C OPE 1078231 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101327 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 18/10/2021 - 08:00 20/10/2021 - 18:00 C OPE 1078227 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 18/10/2021 - 07:00 21/10/2021 - 18:30 C RS 1105365 Released 07/05/2012 - 15:49
BOB HAM 2 NNI G 19/02/2022 - 06:30 20/02/2022 - 19:30 D OPE 1102310 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 08/02/2022 - 07:30 11/02/2022 - 18:30 C OPE 1100921 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 30/10/2021 - 07:30 30/10/2021 - 18:30 D OPE 1107763 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 11/12/2021 - 07:00 13/12/2021 - 18:00 D OPE 1102266 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 23/10/2021 - 07:30 23/10/2021 - 15:30 D OPE 1109978 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 29/11/2021 - 08:00 03/12/2021 - 18:00 C OPE 1078240 Cancelled 07/05/2012 - 15:49
BOB OTA 1 NNI G 08/03/2022 - 07:30 09/03/2022 - 18:30 D RS 1101107 Approved 07/05/2012 - 15:49
BOB OTA 1 NNI G 27/10/2021 - 08:00 27/10/2021 - 17:00 D RS 1107274 Cancelled 07/05/2012 - 15:49
BOB OTA 2 NNI G 10/03/2022 - 07:30 11/03/2022 - 18:30 D RS 1101135 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101328 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 21/10/2021 - 10:00 21/10/2021 - 14:00 D SCA 1107277 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 02/11/2021 - 10:00 02/11/2021 - 14:00 D SCA 1107278 Approved 07/05/2012 - 15:49
BOB T2 NNI G 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097026 Approved 07/05/2012 - 15:49
BOB T2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101329 Approved 07/05/2012 - 15:49
BOB T3 NNI G 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097029 Approved 07/05/2012 - 15:49
BPE 127 215 SNI G 02/12/2021 - 07:30 02/12/2021 - 18:00 D RS 1101611 Approved 07/05/2012 - 15:52
BPE 137 213 SNI G 01/12/2021 - 07:30 01/12/2021 - 18:00 D RS 1101612 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.