Outage planning results

Last updated: Fri, 04/12/2020 - 17:40
Your current search

Sites: all sites selected

Outages search found 3203 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BPE LTN 2 SNI G 03/08/2021 - 07:00 12/08/2021 - 17:00 C RS 1098791 Approved 01/09/2020 - 13:18
LTN WIL 1 SNI G 03/08/2021 - 07:00 12/08/2021 - 17:00 C RS 1098793 Approved 01/09/2020 - 13:21
BPE LTN WIL 1 SNI G 03/08/2021 - 07:00 12/08/2021 - 17:00 C RS 1098672 Approved 07/05/2012 - 15:52
LTN T2 SNI G 03/08/2021 - 07:00 12/08/2021 - 17:00 C RS 1098792 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 09/08/2021 - 07:00 11/08/2021 - 17:00 C RS 1096038 Approved 07/05/2012 - 15:52
MHO T4 SNI G 09/08/2021 - 07:00 11/08/2021 - 17:00 C RS 1096037 Approved 07/05/2012 - 15:52
WIL 220BZ SNI G 11/08/2021 - 08:00 11/08/2021 - 16:00 D RS 1098678 Approved 07/05/2012 - 15:52
WIL 220CBF SNI G 11/08/2021 - 08:00 11/08/2021 - 16:00 D RS 1098679 Approved 07/05/2012 - 15:53
WIL FDR 2252 SNI L 10/08/2021 - 13:30 10/08/2021 - 17:00 D RS 1098685 Approved 10/02/2014 - 13:32
WIL FDR 2162 SNI L 10/08/2021 - 07:00 10/08/2021 - 12:00 D RS 1098681 Approved 10/02/2014 - 13:22
OWH T1 NNI G 02/08/2021 - 07:30 06/08/2021 - 18:30 C RS 1095856 Approved 07/05/2012 - 15:49
OTA WKM 1 NNI G 03/08/2021 - 08:00 05/08/2021 - 18:30 D RS 1097656 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 03/08/2021 - 08:00 05/08/2021 - 18:30 D RS 1097655 Approved 07/05/2012 - 15:49
BPE MHO 1 SNI G 02/08/2021 - 07:00 04/08/2021 - 17:00 C RS 1096036 Approved 07/05/2012 - 15:52
MHO T3 SNI G 02/08/2021 - 07:00 04/08/2021 - 17:00 C RS 1096035 Approved 07/05/2012 - 15:52
WIL MCK SPS SNI G 04/08/2021 - 08:00 04/08/2021 - 16:00 D RS 1098680 Approved 28/08/2014 - 11:11
WIL 220BZ SNI G 03/08/2021 - 08:00 03/08/2021 - 16:00 D RS 1098675 Approved 07/05/2012 - 15:52
WIL 220CBF SNI G 03/08/2021 - 08:00 03/08/2021 - 16:00 D RS 1098677 Approved 07/05/2012 - 15:53
MTI WKM 2 NNI G 27/07/2021 - 08:00 29/07/2021 - 18:30 D RS 1097654 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 27/07/2021 - 08:00 29/07/2021 - 18:30 D RS 1097653 Approved 07/05/2012 - 15:49
MHO FDR 2142 SNI L 26/07/2021 - 07:00 28/07/2021 - 17:00 C RS 1096034 Approved 31/01/2020 - 16:07
ARI KIN 2 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096864 Approved 07/05/2012 - 15:49
KIN T7 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096865 Approved 18/01/2019 - 16:01
KIN 307 317 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096863 Approved 05/03/2020 - 15:17
MTI WKM 1 NNI G 20/07/2021 - 08:00 22/07/2021 - 18:30 D RS 1097652 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.