Outage planning results

Last updated: Mon, 20/09/2021 - 16:40
Your current search

Sites: all sites selected

Outages search found 3907 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WHI FDR 12 SNI L 16/11/2021 - 07:30 16/11/2021 - 18:30 D RS 1108963 Approved 07/05/2012 - 15:53
WHI FDR 13 SNI L 16/11/2021 - 07:30 16/11/2021 - 18:30 D RS 1108964 Approved 07/05/2012 - 15:53
WHI FDR 14 SNI L 16/11/2021 - 07:30 16/11/2021 - 18:30 D RS 1108965 Approved 07/05/2012 - 15:53
WHI R2 SNI L 16/11/2021 - 07:30 16/11/2021 - 18:30 D RS 1108966 Approved 07/05/2012 - 15:52
WHI R2 BP SNI L 16/11/2021 - 07:30 16/11/2021 - 18:30 D RS 1108967 Approved 07/05/2012 - 15:52
WHI R3 SNI L 22/09/2021 - 07:30 22/09/2021 - 17:00 D RS 1105406 Approved 07/05/2012 - 15:52
WHI RTU 1 SNI G 09/11/2021 - 13:00 09/11/2021 - 15:00 D SCA 1107585 Approved 07/05/2012 - 15:52
WHI T1 SNI G 04/04/2022 - 07:30 10/04/2022 - 07:00 C RS 1104139 Approved 07/05/2012 - 15:52
WHI T2 SNI G 16/11/2021 - 07:30 16/11/2021 - 18:30 D RS 1108968 Approved 07/05/2012 - 15:52
WHI T2 SNI G 11/04/2022 - 07:30 17/04/2022 - 07:00 C RS 1104140 Approved 07/05/2012 - 15:52
WHI T3 SNI G 21/09/2021 - 07:00 25/09/2021 - 08:30 C RS 1100284 Approved 07/05/2012 - 15:52
WHI WRK 1 SNI G 14/03/2022 - 07:30 18/03/2022 - 17:00 C RS 1101153 Approved 07/05/2012 - 15:52
WHU FDR 2232 NNI L 24/09/2021 - 06:30 24/09/2021 - 16:00 D RS 1109005 Approved 14/02/2020 - 14:21
WHU T1 NNI G 20/05/2022 - 07:30 20/05/2022 - 18:00 D RS 1101393 Approved 07/05/2012 - 15:49
WHU T3 NNI G 21/09/2021 - 07:30 21/09/2021 - 18:30 D RS 1106039 Approved 07/05/2012 - 15:49
WHU WKO 2 NNI G 23/05/2022 - 08:00 26/05/2022 - 18:00 C RS 1101403 Approved 07/05/2012 - 15:49
WHU WKO 2 NNI G 20/09/2021 - 07:30 29/09/2021 - 18:30 C RS 1100322 Released 07/05/2012 - 15:49
WIL 110BS A PROT1 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108297 Approved 25/08/2021 - 11:09
WIL 110BS A PROT1 SNI G 08/10/2021 - 08:00 08/10/2021 - 17:00 D RS 1108303 Approved 25/08/2021 - 11:09
WIL 110BS A PROT2 SNI G 08/10/2021 - 08:00 08/10/2021 - 17:00 D RS 1108305 Approved 25/08/2021 - 11:23
WIL 110BS A PROT2 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108299 Approved 25/08/2021 - 11:23
WIL 110BS C PROT1 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108302 Approved 25/08/2021 - 11:23
WIL 110BS C PROT1 SNI G 08/10/2021 - 08:00 08/10/2021 - 17:00 D RS 1108306 Approved 25/08/2021 - 11:23
WIL 110BS C PROT2 SNI G 08/10/2021 - 08:00 08/10/2021 - 17:00 D RS 1108304 Approved 25/08/2021 - 11:24
WIL 110BS C PROT2 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108301 Approved 25/08/2021 - 11:24
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.