Outage planning results

Last updated: Mon, 10/08/2020 - 15:10
Your current search

Sites: all sites selected

Outages search found 4035 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WVY 57 134 SNI G 17/08/2020 - 08:00 04/09/2020 - 16:00 C RS 1071475 Approved 07/05/2012 - 15:52
WVY T1 SNI G 17/08/2020 - 08:00 04/09/2020 - 16:00 C RS 1071480 Approved 07/05/2012 - 15:53
BEN 11BS D HVDC H 17/08/2020 - 08:00 18/08/2020 - 18:30 D RS 1087480 Cancelled 15/08/2012 - 11:40
WVY 244 294 304 SNI L 17/08/2020 - 08:00 04/09/2020 - 16:00 C RS 1071472 Approved 07/05/2012 - 15:53
WVY LST 1 SNI L 17/08/2020 - 08:00 04/09/2020 - 16:00 C RS 1071479 Approved 07/05/2012 - 15:52
BEN 11BS B HVDC H 17/08/2020 - 08:00 18/08/2020 - 18:30 D RS 1087479 Cancelled 15/08/2012 - 11:40
MPE 110BZ NNI G 17/08/2020 - 08:00 17/08/2020 - 16:00 D RS 1094333 Approved 18/12/2012 - 13:40
MPE 110CBF NNI G 17/08/2020 - 08:00 17/08/2020 - 16:00 D RS 1094334 Approved 18/12/2012 - 13:40
MPE FDR 262 NNI L 17/08/2020 - 08:00 31/08/2020 - 16:00 C RS 1092514 Approved 09/04/2013 - 08:50
OWH 82 92 107 NNI G 17/08/2020 - 07:30 20/08/2020 - 18:30 C RS 1092347 Approved 07/05/2012 - 15:50
OWH T1 NNI G 17/08/2020 - 07:30 20/08/2020 - 18:30 C RS 1092348 Approved 07/05/2012 - 15:49
SVL FDR 2882 NNI L 17/08/2020 - 07:30 17/08/2020 - 17:30 D RS 1094909 Cancelled 07/05/2012 - 15:50
KPO CB 102 NNI G 17/08/2020 - 07:30 18/08/2020 - 01:30 C RS 1087007 Approved 07/05/2012 - 15:50
WHI R1 BP SNI L 17/08/2020 - 07:30 17/08/2020 - 16:00 D RS 1086525 Approved 07/05/2012 - 15:52
KPO DIS 261 NNI G 17/08/2020 - 07:30 18/08/2020 - 01:30 C CLO 1087011 Approved 22/11/2019 - 10:05
HWA WVY 1 SNI G 17/08/2020 - 07:30 04/09/2020 - 18:30 C RS 1092681 Approved 07/05/2012 - 15:52
EDG OWH 2 NNI G 17/08/2020 - 07:30 20/08/2020 - 18:30 C RS 1092346 Approved 07/05/2012 - 15:49
BEN 11TIE 2997 1137 HVDC H 17/08/2020 - 07:30 18/08/2020 - 18:30 C RS 1095149 Cancelled 27/07/2020 - 09:17
EDG T4 NNI G 17/08/2020 - 07:30 26/02/2021 - 18:30 C RS 1091835 Approved 07/05/2012 - 15:49
CBG CB 2788 NNI G 17/08/2020 - 07:30 18/08/2020 - 01:00 C OPE 1095274 Approved 12/03/2013 - 14:00
WEL T1 NNI G 17/08/2020 - 07:30 27/08/2020 - 08:30 C RS 1089811 Approved 07/05/2012 - 15:49
KPO CB 92 NNI G 17/08/2020 - 07:30 18/08/2020 - 16:00 C RS 1082125 Approved 07/05/2012 - 15:49
KPO 67 94 NNI G 17/08/2020 - 07:30 17/08/2020 - 18:00 D RS 1086996 Approved 12/11/2019 - 09:37
STU 67 76 T5 SI G 17/08/2020 - 07:30 17/08/2020 - 12:29 D RS 1094172 Approved 07/05/2012 - 15:51
KPO BUS A2 NNI G 17/08/2020 - 07:30 08/10/2020 - 09:59 C RS 1087000 Approved 12/11/2019 - 09:43
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.