Outage planning results

Last updated: Thu, 01/10/2020 - 11:40
Your current search

Sites: all sites selected

Outages search found 3938 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB HAM 1 NNI G 09/12/2020 - 20:00 10/12/2020 - 18:30 C OPE 1096223 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 06/03/2021 - 07:00 07/03/2021 - 19:00 D OPE 1088848 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 18/10/2021 - 08:00 20/10/2021 - 18:00 C OPE 1078226 Cancelled 07/05/2012 - 15:49
BOB HAM 1 NNI G 25/10/2021 - 08:00 27/10/2021 - 18:00 C OPE 1078230 Cancelled 07/05/2012 - 15:49
BOB HAM 1 NNI G 06/12/2021 - 08:00 10/12/2021 - 18:00 C OPE 1078243 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 06/12/2021 - 08:00 10/12/2021 - 18:00 C OPE 1078244 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 25/10/2021 - 08:00 27/10/2021 - 18:00 C OPE 1078231 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 18/10/2021 - 08:00 20/10/2021 - 18:00 C OPE 1078227 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 06/03/2021 - 07:00 07/03/2021 - 19:00 D OPE 1088849 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 09/12/2020 - 20:00 10/12/2020 - 18:30 C OPE 1096224 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 29/11/2021 - 08:00 03/12/2021 - 18:00 C OPE 1078240 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 03/10/2020 - 07:00 04/10/2020 - 19:00 D OPE 1088283 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 28/11/2020 - 07:00 28/11/2020 - 18:00 D OPE 1094471 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 02/12/2020 - 07:30 09/12/2020 - 07:29 C OPE 1082264 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 10/10/2020 - 07:00 11/10/2020 - 19:00 D OPE 1088288 Approved 07/05/2012 - 15:49
FHL RDF 1 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D OPE 1096810 Approved 07/05/2012 - 15:52
PEN CB 8612 NNI G 12/10/2020 - 07:00 17/10/2020 - 18:00 C OPE 1095285 Approved 17/03/2014 - 11:42
EDG KAW 1 NNI G 20/11/2020 - 08:30 20/11/2020 - 16:00 D OPE 1096078 Approved 07/05/2012 - 15:49
MPE CB 292 NNI G 14/03/2022 - 07:30 18/03/2022 - 18:30 C OPE 1085177 Approved 07/05/2012 - 15:50
MPE CB 292 NNI G 21/03/2022 - 07:30 25/03/2022 - 18:30 C OPE 1085174 Approved 07/05/2012 - 15:50
MPE CB 292 NNI G 28/03/2022 - 07:30 01/04/2022 - 18:30 C OPE 1085180 Approved 07/05/2012 - 15:50
EDG KAW 2 NNI G 03/11/2020 - 07:30 03/11/2020 - 18:30 D OPE 1095957 Approved 07/05/2012 - 15:49
MPE CB 292 NNI G 29/10/2020 - 07:00 29/10/2020 - 19:00 D OPE 1085708 Cancelled 07/05/2012 - 15:50
MPE CB 292 NNI G 08/03/2021 - 07:30 13/03/2021 - 18:00 C OPE 1085714 Approved 07/05/2012 - 15:50
MPE CB 292 NNI G 17/05/2021 - 07:30 03/06/2021 - 18:00 C OPE 1090394 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.