Outage planning results

Last updated: Thu, 06/08/2020 - 21:40
Your current search

Sites: all sites selected

Outages search found 4054 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ROX 220CBF SI G 06/10/2020 - 10:30 08/10/2020 - 14:00 D RS 1095010 Approved 07/05/2012 - 15:51
PRM FDR 2152 SNI L 06/08/2020 - 08:00 07/08/2020 - 17:00 D RS 1095020 Released 07/05/2012 - 15:53
TGA FDR 11 NNI L 09/11/2020 - 06:30 09/11/2020 - 18:30 D RS 1095021 Approved 07/05/2012 - 15:50
TGA FDR 12 NNI L 09/11/2020 - 06:30 09/11/2020 - 18:30 D RS 1095022 Approved 07/05/2012 - 15:50
PRM FDR 2252 SNI L 13/08/2020 - 08:00 14/08/2020 - 17:00 D RS 1095023 Approved 07/05/2012 - 15:53
TGA FDR 13 NNI L 10/11/2020 - 06:30 10/11/2020 - 18:30 D RS 1095024 Approved 07/05/2012 - 15:50
TGA FDR 14 NNI L 10/11/2020 - 06:30 10/11/2020 - 18:30 D RS 1095025 Approved 07/05/2012 - 15:50
PRM FDR 2232 SNI L 20/08/2020 - 08:00 21/08/2020 - 17:00 D RS 1095026 Approved 07/05/2012 - 15:53
PRM FDR 2182 SNI L 27/08/2020 - 08:00 28/08/2020 - 17:00 D RS 1095027 Approved 07/05/2012 - 15:53
TGA FDR 15 NNI L 11/11/2020 - 06:30 11/11/2020 - 18:30 D RS 1095028 Approved 07/05/2012 - 15:50
INV 220CBF SI G 05/10/2020 - 08:00 09/10/2020 - 18:00 D RS 1095029 Approved 07/05/2012 - 15:51
TGA FDR 16 NNI L 12/11/2020 - 06:30 12/11/2020 - 18:30 D RS 1095030 Approved 07/05/2012 - 15:50
TGA FDR 17 NNI L 12/11/2020 - 06:30 12/11/2020 - 18:30 D RS 1095031 Approved 07/05/2012 - 15:50
TGA FDR 18 NNI L 13/11/2020 - 06:30 13/11/2020 - 18:30 D RS 1095032 Approved 07/05/2012 - 15:50
TGA FDR 19 NNI L 13/11/2020 - 06:30 13/11/2020 - 18:30 D RS 1095033 Approved 07/05/2012 - 15:50
TGA FDR 21 NNI L 16/11/2020 - 06:30 16/11/2020 - 18:30 D RS 1095034 Approved 07/05/2012 - 15:50
TGA FDR 20 NNI L 16/11/2020 - 06:30 16/11/2020 - 18:30 D RS 1095035 Approved 07/05/2012 - 15:50
TGA 11BS B NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095036 Approved 07/05/2012 - 15:50
TGA CB 38 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095037 Approved 07/05/2012 - 15:50
TGA FDR 16 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095038 Approved 07/05/2012 - 15:50
TGA FDR 17 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095039 Approved 07/05/2012 - 15:50
TGA FDR 18 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095040 Approved 07/05/2012 - 15:50
TGA FDR 19 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095041 Approved 07/05/2012 - 15:50
TGA FDR 20 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095042 Approved 07/05/2012 - 15:50
TGA FDR 21 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095043 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.