Outage planning results

Last updated: Thu, 01/10/2020 - 11:40
Your current search

Sites: all sites selected

Outages search found 3938 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ARI 110BZ A NNI G 14/04/2021 - 08:30 14/04/2021 - 16:00 D RS 1096838 Approved 07/05/2012 - 15:50
ARI 110CBF NNI G 14/04/2021 - 08:30 14/04/2021 - 16:00 D RS 1096837 Approved 07/05/2012 - 15:50
EDG 437 414 504 NNI G 08/10/2020 - 07:30 09/10/2020 - 18:00 C RS 1096836 Approved 07/05/2012 - 15:50
EDG KAW 3 NNI G 08/10/2020 - 07:30 09/10/2020 - 18:00 C RS 1096835 Approved 07/05/2012 - 15:49
ARI 110BZ B NNI G 06/04/2021 - 08:30 06/04/2021 - 16:00 D RS 1096834 Approved 07/05/2012 - 15:50
ARI 110BZ A NNI G 06/04/2021 - 08:30 06/04/2021 - 16:00 D RS 1096833 Approved 07/05/2012 - 15:50
HTI RTU 1 NNI G 09/04/2021 - 08:30 09/04/2021 - 12:30 D RS 1096832 Approved 07/05/2012 - 15:49
ARI RTU 1 NNI G 09/04/2021 - 13:00 09/04/2021 - 16:00 D RS 1096831 Approved 07/05/2012 - 15:49
PEN T10 NNI G 09/11/2020 - 07:00 11/11/2020 - 19:00 C OPE 1096828 Approved 07/05/2012 - 15:49
PEN CB 8612 NNI G 09/11/2020 - 07:00 11/11/2020 - 19:00 C OPE 1096827 Approved 17/03/2014 - 11:42
HAY FDR 2782 SNI L 20/10/2020 - 08:00 21/10/2020 - 16:00 C RS 1096826 Approved 07/05/2012 - 15:53
NAP WRK 2 SNI G 05/10/2020 - 06:00 05/10/2020 - 18:00 D RS 1096825 Approved 26/10/2012 - 15:05
NAP 144 154 177 SNI G 05/10/2020 - 06:00 05/10/2020 - 18:00 D RS 1096824 Approved 26/10/2012 - 15:05
FHL 127 144 154 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D OPE 1096814 Approved 07/05/2012 - 15:53
FHL WPW 2 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D OPE 1096813 Approved 07/05/2012 - 15:52
FHL WPW 1 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D OPE 1096812 Approved 07/05/2012 - 15:52
FHL RDF 2 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D OPE 1096811 Approved 07/05/2012 - 15:52
FHL RDF 1 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D OPE 1096810 Approved 07/05/2012 - 15:52
MNG FDR 1052 NNI L 05/10/2020 - 07:30 05/10/2020 - 16:00 D RS 1096803 Approved 07/05/2012 - 15:49
MNG FDR 1112 NNI L 06/10/2020 - 07:30 06/10/2020 - 16:00 D RS 1096802 Approved 07/05/2012 - 15:49
WHU T2 NNI G 05/10/2020 - 08:00 05/10/2020 - 18:30 D RS 1096801 Approved 07/05/2012 - 15:49
HWB FDR 2582 SI L 11/03/2021 - 08:00 12/03/2021 - 17:00 D RS 1096794 Approved 01/05/2018 - 10:33
KMO TMI 1 NNI G 30/11/2020 - 07:30 01/12/2020 - 18:00 D OPE 1096793 Approved 07/05/2012 - 15:50
MTM CB 52 NNI G 30/11/2020 - 07:30 01/12/2020 - 18:00 D OPE 1096792 Approved 07/05/2012 - 15:50
BEN 220BS CHANGE SI G 08/10/2020 - 18:30 08/10/2020 - 19:00 D PSO 1096791 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.