Outage planning results

Last updated: Tue, 19/10/2021 - 12:10
Your current search

Sites: all sites selected

Outages search found 3635 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB HAM 1 NNI G 30/10/2021 - 07:30 30/10/2021 - 18:30 D OPE 1107762 Approved 07/05/2012 - 15:49
MHO 33CBF SNI L 09/11/2021 - 08:00 09/11/2021 - 16:00 D RS 1090062 Approved 31/01/2020 - 16:59
BOB HAM 1 NNI G 19/02/2022 - 06:30 20/02/2022 - 19:30 D OPE 1102309 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 22/02/2022 - 07:30 25/02/2022 - 18:30 D OPE 1101039 Cancelled 07/05/2012 - 15:49
MHO 33BZ K SNI L 22/10/2021 - 08:30 22/10/2021 - 16:00 D RS 1103969 Approved 31/01/2020 - 17:02
BOB HAM 1 NNI G 19/11/2021 - 07:00 21/11/2021 - 18:00 D OPE 1102251 Cancelled 07/05/2012 - 15:49
OWH RTU 1 NNI G 03/12/2021 - 07:30 03/12/2021 - 17:00 D SCA 1106733 Cancelled 07/05/2012 - 15:49
OWH RTU 1 NNI G 10/12/2021 - 07:30 10/12/2021 - 17:00 D SCA 1106734 Cancelled 07/05/2012 - 15:49
WHU FDR 2162 NNI L 21/12/2021 - 08:00 21/12/2021 - 15:30 D RCB 1109815 Approved 14/02/2020 - 14:00
OWH RTU 1 NNI G 21/01/2022 - 07:30 21/01/2022 - 17:00 D SCA 1106737 Cancelled 07/05/2012 - 15:49
EDG 33AFD NNI L 28/01/2022 - 08:00 28/01/2022 - 12:00 D RS 1106430 Approved 27/06/2017 - 13:37
BOB HAM 2 NNI G 30/10/2021 - 07:30 30/10/2021 - 18:30 D OPE 1107763 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 13/11/2021 - 07:30 14/11/2021 - 16:30 D RS 1097025 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 05/09/2022 - 07:30 05/09/2022 - 18:30 D RS 1097018 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101327 Approved 07/05/2012 - 15:49
HEP FDR 2222 NNI L 28/10/2021 - 07:00 28/10/2021 - 12:00 D RS 1104975 Approved 17/11/2015 - 09:58
WGN FDR 2162 SNI L 07/12/2021 - 08:00 07/12/2021 - 16:30 D RS 1109078 Approved 17/06/2020 - 14:20
BOB OTA 1 NNI G 27/10/2021 - 08:00 27/10/2021 - 17:00 D RS 1107274 Cancelled 07/05/2012 - 15:49
WVY CB 112 SNI G 07/11/2021 - 08:00 07/11/2021 - 17:00 D RS 1108320 Approved 18/06/2020 - 14:42
BOB HAM 2 NNI G 19/11/2021 - 07:00 21/11/2021 - 18:00 D OPE 1102252 Cancelled 07/05/2012 - 15:49
BPE MTN WGN 1 PROT2 SNI G 17/02/2022 - 16:00 17/02/2022 - 18:00 D RS 1106751 Approved 18/06/2020 - 15:50
BOB HAM 2 NNI G 22/02/2022 - 07:30 25/02/2022 - 18:30 D OPE 1101036 Cancelled 07/05/2012 - 15:49
BOB HAM 2 NNI G 19/02/2022 - 06:30 20/02/2022 - 19:30 D OPE 1102310 Approved 07/05/2012 - 15:49
BPE MTN WGN 2 PROT2 SNI G 17/02/2022 - 10:00 17/02/2022 - 13:00 D RS 1106744 Approved 18/06/2020 - 15:52
WEL RTU 1 NNI G 07/12/2021 - 10:00 07/12/2021 - 14:00 D SCA 1109098 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.