Outage planning results

Last updated: Sat, 17/04/2021 - 02:40
Your current search

Sites: all sites selected

Outages search found 2128 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
MPE RTU 2 NNI G 19/10/2021 - 07:30 19/10/2021 - 18:30 D RS 1103600 Approved 07/05/2012 - 15:50
HEP ROS 1 NNI G 03/05/2021 - 07:30 07/05/2021 - 18:30 C OPE 1100042 Cancelled 07/05/2012 - 15:49
EDG TRK 2 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1084882 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 13/12/2021 - 07:30 17/12/2021 - 18:30 C RS 1084883 Approved 07/05/2012 - 15:49
BOB 110CBF NNI G 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097017 Approved 07/05/2012 - 15:50
EDG TRK 2 NNI G 24/01/2022 - 07:30 28/01/2022 - 18:30 C RS 1084884 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1084879 Approved 07/05/2012 - 15:49
TGA C 11 NNI G 10/05/2021 - 08:30 10/05/2021 - 13:30 D RS 1101677 Approved 07/05/2012 - 15:50
HEN T5 NNI G 10/05/2021 - 07:30 14/05/2021 - 18:00 C RS 1085561 Approved 07/05/2012 - 15:49
PEN CB 2332B NNI G 17/04/2021 - 07:00 17/04/2021 - 18:00 D CLO 1102780 Approved 03/05/2016 - 09:04
PEN CB 8612 NNI G 09/09/2021 - 07:00 10/09/2021 - 18:00 D OPE 1097840 Approved 17/03/2014 - 11:42
MDN STC 6 HVDC G 17/06/2021 - 07:30 18/06/2021 - 17:30 C RS 1102469 Approved 04/07/2013 - 15:07
EDG TRK 1 NNI G 17/01/2022 - 07:30 21/01/2022 - 18:30 C RS 1084881 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 06/12/2021 - 07:30 10/12/2021 - 18:30 C RS 1084880 Approved 07/05/2012 - 15:49
TGA C 11 NNI G 24/04/2021 - 07:30 24/04/2021 - 13:00 D RS 1099912 Approved 07/05/2012 - 15:50
EDG T8 NNI G 01/04/2021 - 08:30 23/04/2021 - 16:00 C RS 1096644 Released 07/05/2012 - 15:49
EDG OWH 2 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C OPE 1097671 Approved 07/05/2012 - 15:49
TGA C 11 NNI G 24/05/2021 - 08:30 24/05/2021 - 13:30 D RS 1101678 Cancelled 07/05/2012 - 15:50
HEN T3 NNI G 10/05/2021 - 07:30 14/05/2021 - 18:00 C RS 1085560 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 17/04/2021 - 07:30 17/04/2021 - 18:00 D RCB 1103855 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 03/05/2021 - 07:30 03/05/2021 - 19:00 D RS 1088858 Approved 07/05/2012 - 15:49
BOB C 11 NNI G 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097009 Approved 07/05/2012 - 15:50
EDG OWH 2 NNI G 15/11/2021 - 07:30 20/11/2021 - 18:30 C RS 1085188 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 26/10/2021 - 07:30 29/10/2021 - 18:30 C RS 1085189 Approved 07/05/2012 - 15:49
KAW MAT 2 PROT2 NNI G 13/07/2021 - 12:30 13/07/2021 - 16:30 D RS 1103942 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.