Outage planning results

Last updated: Sun, 26/09/2021 - 19:10
Your current search

Sites: all sites selected

Outages search found 3906 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
EDG T7 NNI G 17/01/2022 - 07:30 28/01/2022 - 18:30 C RS 1103115 Approved 07/05/2012 - 15:49
CST SFD 3 SNI G 06/12/2021 - 07:30 11/12/2021 - 18:00 C RS 1100674 Approved 16/11/2018 - 14:41
GFD FDR 22 SNI L 25/01/2022 - 07:30 29/01/2022 - 16:30 C RS 1095066 Approved 07/05/2012 - 15:53
RDF WRK 1 SNI G 24/01/2022 - 07:30 29/01/2022 - 17:00 C RS 1102709 Approved 07/05/2012 - 15:52
DOB RFN IGH 2 SI G 24/01/2022 - 07:30 29/01/2022 - 18:30 C RS 1100818 Approved 20/08/2018 - 12:38
MAN NMA 2 SI G 24/01/2022 - 07:30 29/01/2022 - 18:30 C RS 1082858 Approved 07/05/2012 - 15:51
DOB T11 SI G 24/01/2022 - 07:30 29/01/2022 - 18:30 C RS 1104537 Approved 07/05/2012 - 15:52
TAK T5 NNI G 06/12/2021 - 07:30 11/12/2021 - 18:30 C RS 1085161 Approved 07/05/2012 - 15:49
BPE BRK 2 SNI G 29/11/2021 - 06:30 03/12/2021 - 17:30 C RS 1100642 Approved 07/05/2012 - 15:52
MTO T1 NNI G 14/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1100953 Approved 07/05/2012 - 15:49
ROS 77 107 NNI G 29/11/2021 - 07:00 03/12/2021 - 18:00 C RS 1100649 Approved 07/05/2012 - 15:50
GOR ROX 1 SI G 14/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1100958 Approved 07/05/2012 - 15:51
COL OTI 2 SI G 14/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1100961 Approved 07/05/2012 - 15:51
PEN T23 NNI G 24/01/2022 - 07:00 30/01/2022 - 18:00 C RS 1108234 Approved 07/05/2012 - 15:49
OTA ROS 2 NNI G 29/11/2021 - 07:00 03/12/2021 - 18:00 C RS 1100650 Approved 07/05/2012 - 15:49
TAK T8 NNI G 09/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1097036 Approved 07/05/2012 - 15:49
HEN T1 NNI G 22/11/2021 - 07:30 25/11/2021 - 18:30 C RS 1100616 Approved 07/05/2012 - 15:50
BDE C 1 SI G 17/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1105743 Approved 07/05/2012 - 15:51
ROS T2 NNI G 29/11/2021 - 07:00 03/12/2021 - 18:00 C RS 1100651 Approved 07/05/2012 - 15:49
INV MAN 2 SI G 14/02/2022 - 07:30 19/02/2022 - 18:30 C RS 1082845 Approved 07/05/2012 - 15:51
HAY THW 1B HVDC H 19/02/2022 - 06:00 20/02/2022 - 18:00 C RS 1104751 Approved 16/07/2018 - 11:04
KIN T5 NNI G 14/02/2022 - 07:30 20/02/2022 - 18:30 C RS 1105929 Approved 07/05/2012 - 15:49
ISL CB 768 SI G 25/11/2021 - 07:30 26/11/2021 - 17:30 C RS 1103027 Approved 07/05/2012 - 15:51
BDE C 5 SI G 04/04/2022 - 08:00 06/04/2022 - 16:00 C RS 1104423 Approved 07/05/2012 - 15:51
BDE C 4 SI G 04/04/2022 - 08:00 06/04/2022 - 16:00 C RS 1104422 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.