Outage planning results

Last updated: Fri, 20/05/2022 - 16:10
Your current search

Sites: all sites selected

Outages search found 3581 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HLY 220CBF NNI G 01/08/2022 - 08:30 01/08/2022 - 16:00 D RS 1110860 Approved 07/05/2012 - 15:49
TMU 11kV AFD B2 NNI L 14/06/2022 - 07:30 14/06/2022 - 17:00 D RS 1114910 Approved 03/03/2022 - 08:12
WKM 220CBF SWYD A NNI G 27/06/2022 - 08:00 01/07/2022 - 17:30 D RS 1115017 Approved 07/05/2012 - 15:49
PEN FDR 2092 NNI L 31/01/2023 - 07:30 31/01/2023 - 18:30 D RS 1113270 Approved 07/05/2012 - 15:49
PEN FDR 2112 NNI L 01/02/2023 - 07:30 01/02/2023 - 18:30 D RS 1113272 Approved 07/05/2012 - 15:49
PEN FDR 2122 NNI L 02/02/2023 - 07:30 02/02/2023 - 18:30 D RS 1113274 Approved 07/05/2012 - 15:49
WHU 33kV AFD BUS K NNI L 15/06/2022 - 07:30 15/06/2022 - 17:00 D RS 1114911 Approved 03/03/2022 - 08:17
WKO 110CBF NNI G 24/05/2022 - 08:00 24/05/2022 - 14:00 D RS 1111830 Approved 17/07/2020 - 08:05
HLY 224 357 644 NNI G 26/09/2022 - 07:00 28/09/2022 - 18:00 D RS 1113050 Approved 07/05/2012 - 15:49
WHU 33kV AFD BUS L NNI L 16/06/2022 - 07:30 16/06/2022 - 17:00 D RS 1114912 Approved 03/03/2022 - 08:19
PEN FDR 1702 NNI L 21/01/2023 - 07:30 22/01/2023 - 18:30 D RS 1113239 Approved 07/05/2012 - 15:49
BOB OTA 1 NNI G 10/04/2023 - 07:00 13/04/2023 - 18:00 D RS 1113426 Approved 07/05/2012 - 15:49
PEN CB 1788 NNI L 26/01/2023 - 07:30 26/01/2023 - 18:30 D RS 1113264 Approved 07/05/2012 - 15:49
BOB OTA 1 NNI G 27/02/2023 - 07:00 27/02/2023 - 18:00 D RS 1113325 Approved 07/05/2012 - 15:49
WKO 33kV AFD BUS L NNI L 21/06/2022 - 07:30 21/06/2022 - 17:00 D RS 1114914 Approved 03/03/2022 - 08:21
PEN T10 NNI G 23/01/2023 - 07:30 23/01/2023 - 18:30 D OPE 1113251 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 28/02/2023 - 07:00 28/02/2023 - 18:00 D RS 1113332 Approved 07/05/2012 - 15:49
WKO 33kV AFD BUS K NNI L 20/06/2022 - 07:30 20/06/2022 - 17:00 D RS 1114913 Approved 03/03/2022 - 08:21
FHL FDR 2242 SNI L 13/09/2022 - 12:00 13/09/2022 - 16:00 D RS 1115377 Approved 27/03/2019 - 16:23
FHL WTU GXP TIE 1 SNI G 09/10/2022 - 07:00 09/10/2022 - 17:30 D OTH 1115968 Approved 23/07/2020 - 09:18
PEN T10 NNI G 12/08/2022 - 07:00 12/08/2022 - 18:00 D OPE 1116789 Approved 07/05/2012 - 15:49
BOB T2 NNI G 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097026 Approved 07/05/2012 - 15:49
PEN T10 NNI G 29/06/2022 - 08:30 29/06/2022 - 18:30 D OPE 1115563 Approved 07/05/2012 - 15:49
PEN T10 NNI G 12/07/2022 - 07:00 12/07/2022 - 15:30 D OPE 1116615 Approved 07/05/2012 - 15:49
DRY GLN 1 NNI G 08/09/2022 - 07:00 08/09/2022 - 18:00 D RS 1113024 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.