Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
SVL FDR 2742 NNI L 07/12/2021 - 08:00 08/12/2021 - 16:00 C RS 1100693 Approved 07/05/2012 - 15:50
EDG 220CBF NNI G 27/01/2022 - 08:00 27/01/2022 - 16:00 D RS 1106427 Approved 07/05/2012 - 15:50
SVL FDR 2822 NNI L 09/12/2021 - 08:00 10/12/2021 - 16:00 C RS 1100711 Approved 07/05/2012 - 15:50
EDG 220CBF NNI G 22/11/2021 - 08:00 22/11/2021 - 12:00 D RS 1107416 Approved 07/05/2012 - 15:50
HIN 214 304 237 NNI L 28/05/2022 - 07:30 28/05/2022 - 18:30 D RS 1102161 Approved 07/05/2012 - 15:50
SVL 33BS A NNI L 07/12/2021 - 08:00 08/12/2021 - 16:00 C RS 1100692 Approved 07/05/2012 - 15:50
HIN FDR 302 NNI L 28/05/2022 - 07:30 28/05/2022 - 18:30 D RS 1102165 Approved 07/05/2012 - 15:50
SVL FDR 2862 NNI L 09/12/2021 - 08:00 10/12/2021 - 16:00 C RS 1100713 Approved 07/05/2012 - 15:50
SVL FDR 2842 NNI L 09/12/2021 - 08:00 10/12/2021 - 16:00 C RS 1100712 Approved 07/05/2012 - 15:50
SVL FDR 2882 NNI L 09/12/2021 - 08:00 10/12/2021 - 16:00 C RS 1100714 Approved 07/05/2012 - 15:50
SVL CB 2808 NNI G 09/12/2021 - 08:00 10/12/2021 - 16:00 C RS 1100716 Approved 07/05/2012 - 15:50
SVL CB 2808 NNI G 07/12/2021 - 08:00 08/12/2021 - 16:00 C RS 1100696 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 20/03/2022 - 07:00 20/03/2022 - 18:00 D RS 1109224 Approved 07/05/2012 - 15:50
WAI T1 NNI G 21/11/2021 - 07:30 21/11/2021 - 18:00 D RS 1100597 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 10/04/2022 - 07:00 10/04/2022 - 18:00 D RS 1109238 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 28/03/2022 - 07:00 28/03/2022 - 18:00 D RS 1109234 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 01/05/2022 - 07:00 01/05/2022 - 18:00 D RS 1109251 Approved 07/05/2012 - 15:50
SVL 33BS B NNI L 09/12/2021 - 08:00 10/12/2021 - 16:00 C RS 1100710 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 19/04/2022 - 07:00 19/04/2022 - 18:00 D RS 1109244 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 07/03/2022 - 07:00 07/03/2022 - 18:00 D RS 1109216 Approved 07/05/2012 - 15:50
WAI T5 NNI G 28/10/2021 - 07:00 28/10/2021 - 16:00 D RS 1109684 Approved 07/05/2012 - 15:50
WAI T5 NNI G 21/11/2021 - 07:30 21/11/2021 - 18:00 D RS 1100602 Approved 07/05/2012 - 15:50
WAI T5 NNI G 28/10/2021 - 07:00 28/10/2021 - 16:00 D RS 1109584 Cancelled 07/05/2012 - 15:50
HEP 110BZ A NNI G 01/05/2022 - 07:00 01/05/2022 - 18:00 D RS 1109250 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 20/03/2022 - 07:00 20/03/2022 - 18:00 D RS 1109225 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.