Outage planning results

Last updated: Thu, 26/05/2022 - 13:40
Your current search

Sites: all sites selected

Outages search found 3507 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ARI HAM 2 NNI G 17/01/2023 - 07:30 19/01/2023 - 18:30 C OPE 1113227 Approved 07/05/2012 - 15:49
ARI HAM 2 NNI G 19/11/2022 - 07:30 20/11/2022 - 18:30 C OPE 1113141 Approved 07/05/2012 - 15:49
ARI HAM 2 NNI G 20/06/2022 - 07:00 20/06/2022 - 18:30 D RS 1101443 Approved 07/05/2012 - 15:49
ARI HTI 1 NNI G 25/10/2022 - 08:00 28/10/2022 - 18:30 D RS 1113091 Approved 07/05/2012 - 15:49
ARI KIN 1 NNI G 27/03/2023 - 07:00 27/03/2023 - 18:00 D RS 1113387 Approved 07/05/2012 - 15:49
ARI KIN 2 NNI G 03/10/2022 - 07:30 04/10/2022 - 18:30 D RS 1113073 Approved 07/05/2012 - 15:49
ATI OHK 1 NNI G 19/09/2022 - 07:30 27/09/2022 - 17:30 C RS 1112069 Approved 07/05/2012 - 15:49
ATI OHK 1 NNI G 21/06/2022 - 07:30 01/07/2022 - 17:30 C RS 1112068 Approved 07/05/2012 - 15:49
ATI TRK 1 NNI G 05/07/2022 - 07:30 06/07/2022 - 18:30 C RS 1111011 Approved 07/05/2012 - 15:49
ATI TRK 1 NNI G 07/11/2022 - 07:00 08/11/2022 - 18:00 C RS 1113112 Approved 07/05/2012 - 15:49
ATI TRK 1 NNI G 30/01/2023 - 07:30 31/01/2023 - 18:30 C RS 1113263 Approved 07/05/2012 - 15:49
ATI TRK 2 NNI G 25/01/2023 - 07:30 26/01/2023 - 18:30 C RS 1113259 Approved 07/05/2012 - 15:49
ATI TRK 2 NNI G 18/07/2022 - 07:30 19/07/2022 - 18:30 C RS 1111015 Approved 07/05/2012 - 15:49
ATI WKM 1 NNI G 23/01/2023 - 07:00 24/01/2023 - 18:00 C RS 1113243 Approved 07/05/2012 - 15:49
BOB 247 278 NNI G 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097027 Approved 07/05/2012 - 15:50
OTA CB 488 NNI G 30/06/2022 - 07:00 01/07/2022 - 18:00 C RS 1109628 Approved 07/05/2012 - 15:50
BOB 247 278 NNI G 13/09/2022 - 07:00 13/09/2022 - 18:00 D RS 1114458 Approved 07/05/2012 - 15:50
DRY GLN 2 NNI G 25/08/2022 - 07:30 26/08/2022 - 18:00 C RS 1116412 Approved 07/05/2012 - 15:50
BOB 247 278 NNI G 23/09/2022 - 07:00 23/09/2022 - 18:00 D RS 1114560 Approved 07/05/2012 - 15:50
BOB HAM 1 NNI G 13/10/2022 - 06:00 13/10/2022 - 18:00 D RS 1116773 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 12/09/2022 - 07:30 14/09/2022 - 18:30 C RS 1113038 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 19/11/2022 - 07:30 20/11/2022 - 18:30 C OPE 1113139 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 17/01/2023 - 07:30 19/01/2023 - 18:30 C OPE 1113224 Approved 07/05/2012 - 15:49
BOB HAM 1 NNI G 24/01/2023 - 07:30 26/01/2023 - 18:30 C OPE 1113253 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 05/09/2022 - 07:00 09/09/2022 - 18:00 C RS 1097018 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.