Outage planning results

Last updated: Sat, 08/08/2020 - 12:40
Your current search

Sites: all sites selected

Outages search found 4034 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WWD CB 262 SNI G 12/12/2020 - 07:30 13/12/2020 - 18:00 C RS 1095283 Approved 07/05/2012 - 15:53
CPK T3 SNI G 12/12/2020 - 07:30 13/12/2020 - 18:00 D RS 1095282 Approved 07/05/2012 - 15:52
CPK WWD WIL 3 SNI G 12/12/2020 - 07:30 13/12/2020 - 18:00 D RS 1095281 Approved 07/05/2012 - 15:52
WWD CB 242 SNI G 05/12/2020 - 07:30 06/12/2020 - 18:00 C RS 1095280 Approved 07/05/2012 - 15:53
CPK T4 SNI G 05/12/2020 - 07:30 06/12/2020 - 18:00 D RS 1095279 Approved 07/05/2012 - 15:52
CPK WWD WIL 2 SNI G 05/12/2020 - 07:30 06/12/2020 - 18:00 D RS 1095278 Approved 07/05/2012 - 15:52
OTA WKM 2 NNI G 27/09/2020 - 07:30 27/09/2020 - 18:00 D RS 1095276 Approved 07/05/2012 - 15:49
OTA WKM 1 NNI G 26/09/2020 - 07:30 26/09/2020 - 18:00 D RS 1095275 Approved 07/05/2012 - 15:49
CBG CB 2788 NNI G 17/08/2020 - 07:30 18/08/2020 - 01:00 C OPE 1095274 Approved 12/03/2013 - 14:00
KAW FDR 2752 NNI L 18/08/2020 - 08:00 18/08/2020 - 12:00 D RS 1095273 Approved 19/09/2017 - 11:18
PTS 270598 MAN ROX SI G 20/04/2021 - 09:00 20/04/2021 - 13:00 D RS 1095264 Approved 24/02/2015 - 13:48
PTS 1886 CML FKN SI G 02/03/2021 - 09:00 02/03/2021 - 13:00 D RS 1095263 Approved 07/05/2012 - 15:52
PTS 1950 SDN TMH SI G 04/11/2020 - 09:00 04/11/2020 - 13:00 D RS 1095262 Approved 07/05/2012 - 15:52
PTS 1949 HWB TMH SI G 03/11/2020 - 13:00 03/11/2020 - 16:00 D RS 1095261 Approved 07/05/2012 - 15:52
PTS 1892 ROX TWI SI G 13/10/2020 - 13:00 13/10/2020 - 16:00 D RS 1095260 Approved 19/12/2012 - 10:40
ISL 66CBF SI G 24/09/2020 - 08:30 24/09/2020 - 12:30 D RS 1095259 Approved 07/05/2012 - 15:51
ISL 66BZ SI G 24/09/2020 - 08:30 24/09/2020 - 12:30 D RS 1095258 Approved 07/05/2012 - 15:51
ISL 66CBF SI G 20/08/2020 - 08:30 20/08/2020 - 12:30 D RS 1095257 Approved 07/05/2012 - 15:51
ISL 66BZ SI G 20/08/2020 - 08:30 20/08/2020 - 12:30 D RS 1095256 Approved 07/05/2012 - 15:51
KPU FDR 1052 NNI L 26/08/2020 - 08:00 26/08/2020 - 16:00 D RS 1095253 Approved 07/05/2012 - 15:49
SVL FDR 2882 NNI L 15/09/2020 - 07:30 15/09/2020 - 17:30 D RS 1095248 Approved 07/05/2012 - 15:50
SVL RTU 1 NNI G 09/09/2020 - 10:00 09/09/2020 - 16:00 D SCA 1095247 Approved 07/05/2012 - 15:50
OWH RTU 1 NNI G 25/11/2020 - 08:00 25/11/2020 - 18:00 D RS 1095244 Approved 07/05/2012 - 15:49
MAT RTU 1 NNI G 02/12/2020 - 07:00 02/12/2020 - 18:00 D RS 1095243 Approved 07/05/2012 - 15:49
KAW MAT 2 PROT1 NNI G 02/12/2020 - 12:30 02/12/2020 - 15:00 D RS 1095242 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.