Outage planning results

Last updated: Thu, 22/10/2020 - 14:10
Your current search

Sites: all sites selected

Outages search found 3612 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB FDR 302 NNI L 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097012 Approved 07/05/2012 - 15:50
BOB FDR 312 NNI L 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097013 Approved 07/05/2012 - 15:50
BOB C 11 NNI G 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097009 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097017 Approved 07/05/2012 - 15:50
BOB CB 282 NNI G 20/10/2021 - 08:00 20/10/2021 - 17:00 D RS 1097011 Approved 07/05/2012 - 15:50
TAK T8 NNI G 11/10/2021 - 07:30 16/10/2021 - 18:30 C RS 1085163 Approved 07/05/2012 - 15:49
HLY OTA 2 NNI G 11/10/2021 - 07:30 16/10/2021 - 18:30 C RS 1085162 Approved 07/05/2012 - 15:49
TAK T5 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085157 Approved 07/05/2012 - 15:49
DRY OTA 1 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085156 Approved 07/05/2012 - 15:50
OWH TMI TRK 1 NNI G 04/10/2021 - 07:30 08/10/2021 - 18:30 C RS 1085186 Approved 07/05/2012 - 15:50
OTA ROS 1 NNI G 16/03/2020 - 07:00 24/09/2021 - 16:00 C RS 1089181 Released 07/05/2012 - 15:49
MHO FDR 2142 SNI L 14/09/2021 - 07:00 15/09/2021 - 17:00 C RS 1094120 Approved 31/01/2020 - 16:07
OWH T2 NNI G 30/08/2021 - 07:30 03/09/2021 - 18:30 C RS 1095857 Approved 07/05/2012 - 15:49
MHO RTU 1 SNI G 17/08/2021 - 08:00 18/08/2021 - 16:00 D RS 1090069 Approved 07/05/2012 - 15:52
MHO 33BZ SNI L 16/08/2021 - 08:00 16/08/2021 - 16:00 D RS 1090059 Approved 31/01/2020 - 16:42
MHO 33CBF SNI L 16/08/2021 - 08:00 16/08/2021 - 16:00 D RS 1090062 Approved 31/01/2020 - 16:59
BPE MHO 2 SNI G 09/08/2021 - 07:00 11/08/2021 - 17:00 C RS 1096038 Approved 07/05/2012 - 15:52
MHO T4 SNI G 09/08/2021 - 07:00 11/08/2021 - 17:00 C RS 1096037 Approved 07/05/2012 - 15:52
OWH T1 NNI G 02/08/2021 - 07:30 06/08/2021 - 18:30 C RS 1095856 Approved 07/05/2012 - 15:49
BPE MHO 1 SNI G 02/08/2021 - 07:00 04/08/2021 - 17:00 C RS 1096036 Approved 07/05/2012 - 15:52
MHO T3 SNI G 02/08/2021 - 07:00 04/08/2021 - 17:00 C RS 1096035 Approved 07/05/2012 - 15:52
MHO FDR 2142 SNI L 26/07/2021 - 07:00 28/07/2021 - 17:00 C RS 1096034 Approved 31/01/2020 - 16:07
KIN T7 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096865 Approved 18/01/2019 - 16:01
KIN 307 317 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096863 Approved 05/03/2020 - 15:17
ARI KIN 2 NNI G 22/07/2021 - 07:30 23/07/2021 - 18:30 C RS 1096864 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.