Outage planning results

Last updated: Fri, 18/09/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 4079 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
EDG KAW 1 NNI G 03/11/2020 - 07:30 03/11/2020 - 18:30 D RS 1095320 Approved 07/05/2012 - 15:49
EDG KAW 2 NNI G 09/02/2021 - 07:30 11/02/2021 - 18:00 D RS 1085459 Approved 07/05/2012 - 15:49
EDG KAW 2 NNI G 03/11/2020 - 07:30 03/11/2020 - 18:30 D OPE 1095957 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 27/01/2021 - 07:30 27/01/2021 - 17:30 D RS 1095622 Approved 07/05/2012 - 15:49
EDG WAI 2 NNI G 15/11/2020 - 07:30 15/11/2020 - 18:00 D RS 1090647 Cancelled 07/05/2012 - 15:49
KPO CB 252 NNI G 02/11/2020 - 07:30 02/11/2020 - 18:00 D RS 1088185 Approved 12/11/2019 - 09:46
GLN T4 NNI G 30/11/2020 - 07:00 30/11/2020 - 18:00 D RS 1085504 Approved 07/05/2012 - 15:49
KPO 67 104 NNI G 02/11/2020 - 07:30 02/11/2020 - 18:00 D RS 1088187 Approved 12/11/2019 - 09:56
ISL 220BS A SI G 26/12/2020 - 07:30 26/12/2020 - 18:30 D RS 1087172 Approved 07/05/2012 - 15:51
KPO BUS A3 NNI G 02/11/2020 - 07:30 02/11/2020 - 18:00 D RS 1088188 Approved 12/11/2019 - 09:57
HAM KPO 1 NNI G 02/05/2021 - 07:30 02/05/2021 - 18:00 D RS 1088389 Approved 07/05/2012 - 15:49
ISL 220BS B SI G 06/11/2020 - 07:30 06/11/2020 - 18:30 D RS 1087188 Cancelled 07/05/2012 - 15:51
HAM KPO 1 NNI G 08/03/2021 - 07:00 12/03/2021 - 18:00 D RS 1085524 Cancelled 07/05/2012 - 15:49
KPO BUS A3 NNI G 13/06/2021 - 07:30 13/06/2021 - 18:00 D RS 1088399 Approved 12/11/2019 - 09:57
HAM KPO 2 NNI G 23/02/2021 - 07:30 23/02/2021 - 18:00 D RS 1088258 Cancelled 07/05/2012 - 15:49
KPO BUS A3 NNI G 19/04/2021 - 07:30 19/04/2021 - 18:00 D RS 1088367 Approved 12/11/2019 - 09:57
DRY GLN 1 NNI G 19/04/2021 - 07:00 19/04/2021 - 18:00 D RS 1085448 Approved 07/05/2012 - 15:50
KPO BUS A3 NNI G 02/05/2021 - 07:30 02/05/2021 - 18:00 D RS 1088387 Approved 12/11/2019 - 09:57
HAM T2 NNI G 08/03/2021 - 07:00 12/03/2021 - 18:00 D RS 1085533 Cancelled 07/05/2012 - 15:49
KPO BUS A3 NNI G 15/03/2021 - 07:30 15/03/2021 - 18:00 D RS 1088363 Approved 12/11/2019 - 09:57
ISL 66BS A SI G 14/04/2021 - 07:30 15/04/2021 - 18:30 D RS 1087204 Approved 07/05/2012 - 15:51
ISL 66BS A SI G 07/04/2021 - 07:30 08/04/2021 - 18:30 D RS 1087209 Approved 07/05/2012 - 15:51
ISL 66BS A SI G 30/04/2021 - 07:30 30/04/2021 - 18:30 D RS 1087201 Approved 07/05/2012 - 15:51
HLY CB 362 NNI G 03/03/2021 - 07:30 03/03/2021 - 19:00 D RS 1085573 Approved 07/05/2012 - 15:49
HLY CB 262 NNI G 03/03/2021 - 07:30 03/03/2021 - 19:00 D RS 1085572 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.