Outage planning results

Last updated: Tue, 09/08/2022 - 07:10
Your current search

Sites: all sites selected

Outages search found 3136 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ARI HAM 1 NNI G 19/11/2022 - 07:30 20/11/2022 - 18:30 C RS 1113134 Approved 07/05/2012 - 15:49
HAM KPO 1 NNI G 10/04/2023 - 07:00 11/04/2023 - 18:00 C RS 1113429 Approved 07/05/2012 - 15:49
ALB T6 NNI G 05/12/2022 - 07:30 09/12/2022 - 18:30 C RS 1113177 Approved 07/05/2012 - 15:49
HAM KPO 2 NNI G 10/10/2022 - 07:30 11/10/2022 - 18:30 D RS 1113079 Cancelled 07/05/2012 - 15:49
HAM KPO 2 NNI G 15/05/2023 - 07:30 19/05/2023 - 18:30 C RS 1114205 Approved 07/05/2012 - 15:49
HAM T7 NNI G 15/08/2022 - 07:00 29/08/2022 - 17:00 C RS 1116604 Approved 07/05/2012 - 15:49
PEN 33BZ NNI L 12/06/2023 - 07:30 13/06/2023 - 18:30 D RS 1113508 Approved 23/04/2013 - 09:10
HAM T8 NNI G 25/08/2022 - 07:30 25/08/2022 - 18:30 D RS 1112998 Cancelled 07/05/2012 - 15:49
HEN SWN 1 NNI G 08/05/2023 - 08:00 11/05/2023 - 18:30 C RS 1113478 Cancelled 07/05/2012 - 15:49
HAM PAO WHU 1 NNI G 31/10/2022 - 07:30 02/11/2022 - 18:00 C RS 1113094 Approved 07/05/2012 - 15:49
EDG KAW 3 NNI G 12/09/2022 - 07:00 15/09/2022 - 18:30 C RS 1113036 Approved 07/05/2012 - 15:49
HAM PAO WHU 2 NNI G 15/08/2022 - 08:00 15/08/2022 - 12:30 D RS 1117069 Approved 07/05/2012 - 15:49
HAM PAO WHU 2 NNI G 15/11/2022 - 07:30 16/11/2022 - 18:30 C RS 1113128 Approved 07/05/2012 - 15:49
HAM PAO WHU 2 NNI G 17/04/2023 - 07:30 28/04/2023 - 18:30 C RS 1113441 Approved 07/05/2012 - 15:49
EDG KAW 1 NNI G 05/12/2022 - 07:30 06/12/2022 - 18:30 C RS 1113179 Approved 07/05/2012 - 15:49
HEN CB 488 NNI G 28/11/2022 - 07:30 02/12/2022 - 18:30 C RS 1116466 Approved 07/05/2012 - 15:49
ALB T3 NNI G 27/02/2023 - 07:30 05/03/2023 - 18:30 C RS 1116441 Approved 07/05/2012 - 15:49
HEN C 1 NNI G 31/10/2022 - 07:30 04/11/2022 - 18:30 C RS 1113101 Approved 07/05/2012 - 15:49
CBG T4 NNI G 03/10/2022 - 07:00 06/10/2022 - 18:30 D RS 1113068 Cancelled 07/05/2012 - 15:49
HEN HEP 2 NNI G 08/11/2022 - 07:30 11/11/2022 - 18:30 C RS 1117129 Approved 07/05/2012 - 15:49
HEN HEP 3 NNI G 05/10/2022 - 07:00 07/10/2022 - 18:00 C RS 1113076 Approved 07/05/2012 - 15:49
HEN HEP 4 NNI G 14/12/2022 - 07:30 16/12/2022 - 18:30 C RS 1113202 Approved 07/05/2012 - 15:49
CBG T4 NNI G 10/04/2023 - 07:00 11/04/2023 - 18:00 C RS 1113430 Approved 07/05/2012 - 15:49
ALB T3 NNI G 26/10/2022 - 07:30 27/10/2022 - 18:30 C RS 1106268 Approved 07/05/2012 - 15:49
CBG T4 NNI G 06/03/2023 - 07:00 07/03/2023 - 18:00 D RS 1113343 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.