Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HAM FDR 2132 NNI L 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091973 Approved 07/05/2012 - 15:51
HAM FDR 2142 NNI L 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091974 Approved 07/05/2012 - 15:51
HAM FDR 2152 NNI L 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091975 Approved 07/05/2012 - 15:51
HAM FDR 2172 NNI L 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091976 Approved 07/05/2012 - 15:51
HAM FDR 2182 NNI L 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091977 Approved 07/05/2012 - 15:51
HAM CB 2198 NNI G 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091970 Approved 07/05/2012 - 15:51
HAM 33BS A NNI L 16/10/2020 - 07:30 19/10/2020 - 18:00 C RS 1091969 Approved 07/05/2012 - 15:51
ALB C 1 NNI G 14/06/2021 - 07:30 25/06/2021 - 18:00 C RS 1085379 Approved 07/05/2012 - 15:49
ALB FDR 262 NNI L 25/01/2021 - 07:30 29/01/2021 - 18:00 C RS 1085384 Approved 07/05/2012 - 15:49
CBG T3 NNI G 09/12/2020 - 07:30 10/12/2020 - 18:00 C RS 1088817 Approved 07/05/2012 - 15:49
ALB HEN 1 NNI G 09/11/2020 - 07:30 11/11/2020 - 18:00 C RS 1085385 Approved 07/05/2012 - 15:49
ALB HEN 1 NNI G 26/02/2021 - 08:00 05/03/2021 - 18:00 C RS 1090776 Approved 07/05/2012 - 15:49
EDG KAW 3 NNI G 28/10/2020 - 07:30 29/10/2020 - 18:00 C RS 1088178 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 21/09/2020 - 07:30 22/09/2020 - 18:30 C OPE 1095532 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 26/10/2021 - 07:30 29/10/2021 - 18:30 C RS 1085189 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 15/11/2021 - 07:30 20/11/2021 - 18:30 C RS 1085188 Approved 07/05/2012 - 15:49
EDG T4 NNI G 28/09/2020 - 07:30 02/10/2020 - 18:00 C RS 1085462 Cancelled 07/05/2012 - 15:49
EDG T5 NNI G 28/09/2020 - 07:30 30/09/2020 - 18:00 C RS 1085464 Cancelled 07/05/2012 - 15:49
EDG T5 NNI G 14/09/2020 - 07:30 16/10/2020 - 16:00 C RS 1095100 Approved 07/05/2012 - 15:49
EDG T7 NNI G 08/10/2020 - 07:30 09/10/2020 - 18:30 C RS 1086063 Approved 07/05/2012 - 15:49
EDG T8 NNI G 12/10/2020 - 07:30 26/02/2021 - 18:30 C RS 1090705 Cancelled 07/05/2012 - 15:49
EDG TRK 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1084879 Approved 07/05/2012 - 15:49
BPE TWC LTN 1 SNI G 29/03/2021 - 07:00 01/04/2021 - 18:30 C RS 1086150 Approved 07/05/2012 - 15:53
HAM WKM 1 NNI G 10/10/2020 - 07:00 11/10/2020 - 19:00 C RS 1088007 Approved 07/05/2012 - 15:49
HAM PAO WHU 2 NNI G 27/08/2020 - 07:30 28/08/2020 - 18:30 C RS 1092045 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.