Outage planning results

Last updated: Sat, 24/10/2020 - 12:40
Your current search

Sites: all sites selected

Outages search found 3557 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
MTO T1 NNI G 02/11/2020 - 07:00 04/11/2020 - 18:00 C RS 1092279 Approved 07/05/2012 - 15:49
WEL T2 NNI G 02/11/2020 - 07:00 04/11/2020 - 18:00 C RS 1092280 Approved 07/05/2012 - 15:49
KAI T1 SI G 27/10/2020 - 07:30 30/10/2020 - 17:30 C RS 1087231 Approved 07/05/2012 - 15:51
HWB FDR 2652 SI L 27/10/2020 - 08:30 28/10/2020 - 16:30 C RS 1096768 Approved 07/05/2012 - 15:52
WIR T2 NNI G 02/11/2020 - 07:30 04/11/2020 - 18:00 C RS 1096746 Approved 07/05/2012 - 15:49
GFD HAY 2 SNI G 27/10/2020 - 07:30 30/10/2020 - 18:00 C RS 1086241 Approved 07/05/2012 - 15:52
GFD T5 SNI G 27/10/2020 - 07:30 30/10/2020 - 18:00 C RS 1086242 Approved 07/05/2012 - 15:52
INV 687 743 SI G 02/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1087158 Approved 07/05/2012 - 15:51
SDN 427 437 497 SI G 03/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1087336 Approved 07/05/2012 - 15:51
SDN T2 SI G 03/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1087339 Approved 07/05/2012 - 15:51
STK C 33 SI G 24/11/2020 - 07:30 25/11/2020 - 18:30 C RS 1095222 Approved 07/05/2012 - 15:52
THI 415 413 425 SNI G 07/11/2020 - 18:30 26/11/2020 - 10:00 C RS 1096712 Approved 28/05/2014 - 13:32
THI CB 422 SNI G 07/11/2020 - 18:30 26/11/2020 - 10:00 C RS 1097410 Approved 23/07/2012 - 14:50
OWH TMI TRK 1 NNI G 23/11/2020 - 07:00 26/11/2020 - 17:00 C RS 1085791 Approved 07/05/2012 - 15:50
TKR WIL 2 SNI G 27/10/2020 - 07:00 30/10/2020 - 18:30 C RS 1086483 Approved 07/05/2012 - 15:52
INV T5 SI G 02/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1096966 Approved 07/05/2012 - 15:51
INV CB 742 SI G 02/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1096967 Approved 07/05/2012 - 15:51
COL OTI 2 SI G 27/10/2020 - 06:30 30/10/2020 - 18:30 C RS 1093338 Approved 07/05/2012 - 15:51
CLH COL 1 SI G 27/10/2020 - 06:30 30/10/2020 - 18:30 C RS 1093339 Approved 07/05/2012 - 15:51
WHI FDR 2802 SNI L 02/11/2020 - 10:00 05/11/2020 - 16:00 C RS 1097341 Approved 07/05/2012 - 15:53
WHI FDR 2822 SNI L 02/11/2020 - 10:00 05/11/2020 - 16:00 C RS 1097342 Approved 07/05/2012 - 15:53
WHI FDR 2832 SNI L 02/11/2020 - 10:00 05/11/2020 - 16:00 C RS 1097343 Approved 07/05/2012 - 15:53
WHI FDR 2842 SNI L 02/11/2020 - 10:00 05/11/2020 - 16:00 C RS 1097344 Approved 07/05/2012 - 15:53
DRY OTA 1 NNI G 23/11/2020 - 07:30 27/11/2020 - 18:30 C RS 1095821 Approved 07/05/2012 - 15:50
DOB RFN IGH 2 SI G 23/11/2020 - 07:00 27/11/2020 - 18:30 C RS 1095512 Approved 20/08/2018 - 12:38
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.