Outage planning results

Last updated: Fri, 27/05/2022 - 18:40
Your current search

Sites: all sites selected

Outages search found 3469 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BEN HAY 1 HVDC H 22/06/2022 - 07:30 22/06/2022 - 17:00 D RCB 1116969 Approved 07/05/2012 - 15:49
BEN HAY 1 HVDC H 20/06/2022 - 07:30 20/06/2022 - 17:00 D RCB 1116961 Approved 07/05/2012 - 15:49
BPE PRM HAY 1 SNI G 30/05/2022 - 08:00 30/05/2022 - 16:00 D RCB 1116491 Approved 16/10/2014 - 10:31
BOB 110CBF NNI G 12/09/2022 - 07:00 12/09/2022 - 18:00 D RS 1114454 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 08/09/2022 - 07:30 08/09/2022 - 18:00 D RS 1115864 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 06/10/2022 - 08:00 06/10/2022 - 16:00 D RS 1116770 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 15/09/2022 - 07:30 15/09/2022 - 18:00 D RS 1111606 Cancelled 07/05/2012 - 15:50
ROS FDR 2372 NNI L 13/06/2022 - 07:00 24/06/2022 - 15:00 C RS 1117026 Approved 23/03/2018 - 10:02
OWH 110BZ NNI G 12/07/2022 - 08:00 12/07/2022 - 16:30 D RS 1106678 Approved 29/05/2017 - 11:25
TGA C 11 NNI G 03/04/2023 - 07:30 04/04/2023 - 18:30 C RS 1113407 Approved 07/05/2012 - 15:50
TMU CB 39 NNI L 19/09/2022 - 07:00 23/09/2022 - 16:00 C RS 1114749 Approved 07/05/2012 - 15:50
ROS FDR 2352 NNI L 30/05/2022 - 07:00 10/06/2022 - 15:00 C RS 1116165 Approved 23/03/2018 - 10:01
OTA CB 478 NNI G 27/07/2022 - 07:00 29/07/2022 - 18:00 C RS 1112958 Approved 07/05/2012 - 15:50
OTA CB 478 NNI G 30/06/2022 - 07:00 01/07/2022 - 18:00 C RS 1109630 Approved 07/05/2012 - 15:50
TMU CB 37 NNI L 05/09/2022 - 07:00 09/09/2022 - 16:00 C RS 1114747 Approved 07/05/2012 - 15:50
OTA CB 478 NNI G 11/11/2022 - 07:30 11/11/2022 - 18:30 D RS 1112952 Approved 07/05/2012 - 15:50
OTA CB 488 NNI G 09/11/2022 - 07:30 10/11/2022 - 18:30 D RS 1112942 Approved 07/05/2012 - 15:50
OTA CB 478 NNI G 26/07/2022 - 07:00 26/07/2022 - 18:00 D RS 1112955 Approved 07/05/2012 - 15:50
KMO TRK 2 PROT2 NNI G 10/06/2022 - 12:00 10/06/2022 - 15:00 D RS 1115004 Cancelled 07/05/2012 - 15:50
TWH RTU 2 NNI G 30/11/2022 - 08:00 30/11/2022 - 12:00 D RS 1114499 Approved 19/10/2017 - 12:23
OWH 110BZ NNI G 18/07/2022 - 08:00 18/07/2022 - 16:30 D RS 1106684 Approved 29/05/2017 - 11:25
DRY HLY 2 NNI G 29/08/2022 - 07:30 01/09/2022 - 18:00 C RS 1111023 Approved 03/11/2021 - 15:01
OTA CB 488 NNI G 30/06/2022 - 07:00 01/07/2022 - 18:00 C RS 1109628 Approved 07/05/2012 - 15:50
OTA CB 488 NNI G 27/07/2022 - 07:00 27/07/2022 - 18:00 D RS 1115484 Approved 07/05/2012 - 15:50
KMO TRK 1 PROT2 NNI G 10/06/2022 - 08:00 10/06/2022 - 11:00 D RS 1115003 Cancelled 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.