Outage planning results

Last updated: Mon, 14/06/2021 - 07:40
Your current search

Sites: all sites selected

Outages search found 3546 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
MDN 220BZ NNI G 04/05/2022 - 08:00 04/05/2022 - 18:00 D RS 1101352 Approved 07/05/2012 - 15:49
HEN CB 288 NNI G 03/05/2022 - 07:30 03/05/2022 - 18:30 D RS 1101343 Approved 07/05/2012 - 15:49
HEN 110BZ NNI G 03/05/2022 - 07:30 03/05/2022 - 18:30 D RS 1101344 Approved 07/05/2012 - 15:50
HEN 110CBF NNI G 03/05/2022 - 07:30 03/05/2022 - 18:30 D RS 1101345 Approved 07/05/2012 - 15:50
CUL RTU 1 SI G 03/05/2022 - 08:00 03/05/2022 - 18:30 D RS 1101350 Approved 07/05/2012 - 15:51
CUL RTU 2 SI G 03/05/2022 - 08:00 03/05/2022 - 18:30 D RS 1101349 Approved 07/05/2012 - 15:52
WKM WRK 1 SNI G 02/05/2022 - 07:30 03/05/2022 - 18:30 C RS 1102663 Cancelled 16/10/2013 - 10:02
MDN 110BZ NNI G 03/05/2022 - 08:00 03/05/2022 - 18:00 D RS 1101348 Approved 07/05/2012 - 15:50
HEP C 13 NNI G 19/04/2022 - 07:30 02/05/2022 - 18:30 C RS 1103135 Approved 07/05/2012 - 15:50
WRK RTU 1 SNI G 02/05/2022 - 07:30 02/05/2022 - 17:00 D RS 1102662 Approved 07/05/2012 - 15:52
BOB FDR 212 NNI L 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101326 Approved 07/05/2012 - 15:49
BOB 214 227 267 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101325 Approved 07/05/2012 - 15:50
ARI BOB 1 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101324 Approved 07/05/2012 - 15:50
BOB HAM 2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101327 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101328 Approved 07/05/2012 - 15:49
BOB T2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101329 Approved 07/05/2012 - 15:49
MTI WKM 1 NNI G 30/04/2022 - 07:30 01/05/2022 - 18:30 D RS 1101323 Approved 07/05/2012 - 15:49
LIV NSY 1 SI G 18/01/2022 - 07:30 29/04/2022 - 18:30 C RS 1099267 Approved 07/05/2012 - 15:51
BRY ISL 1 SI G 26/04/2022 - 06:30 29/04/2022 - 18:30 C RS 1101312 Approved 07/05/2012 - 15:51
DOB T12 SI G 27/04/2022 - 07:00 29/04/2022 - 18:30 C RS 1104538 Approved 07/05/2012 - 15:52
HWB FDR 2602 SI L 26/04/2022 - 07:30 29/04/2022 - 18:30 C RS 1101315 Approved 07/05/2012 - 15:52
ATU DOB 1 SI G 27/04/2022 - 07:00 29/04/2022 - 18:30 C RS 1101319 Approved 20/08/2018 - 12:36
OTA T11 NNI G 01/03/2022 - 07:30 29/04/2022 - 18:30 C RS 1101064 Cancelled 07/05/2012 - 15:49
OTA T11 NNI G 01/03/2022 - 07:30 29/04/2022 - 18:30 C RS 1079549 Approved 07/05/2012 - 15:49
MPE CB 252 NNI G 27/04/2022 - 07:00 29/04/2022 - 18:00 C OPE 1101317 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.