Outage planning results

Last updated: Sun, 07/03/2021 - 20:40
Your current search

Sites: all sites selected

Outages search found 2288 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB T3 NNI G 13/11/2021 - 07:30 13/11/2021 - 16:30 D RS 1097029 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 13/11/2021 - 07:30 13/11/2021 - 16:30 D RS 1097028 Approved 07/05/2012 - 15:49
BOB 227 247 267 NNI G 13/11/2021 - 07:30 13/11/2021 - 16:30 D RS 1097024 Approved 07/05/2012 - 15:49
HAY T5 SNI G 13/11/2021 - 06:00 13/11/2021 - 18:00 D RS 1098930 Cancelled 07/05/2012 - 15:52
TUI CB 128 SNI G 11/11/2021 - 07:30 11/11/2021 - 18:00 D RS 1098995 Cancelled 07/05/2012 - 15:52
EDG TRK 2 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1084882 Approved 07/05/2012 - 15:49
TAK T8 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1085165 Approved 07/05/2012 - 15:49
HLY OTA 2 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1085164 Approved 07/05/2012 - 15:49
DVK T2 SNI G 08/11/2021 - 07:30 12/11/2021 - 17:30 D RS 1098892 Cancelled 07/05/2012 - 15:52
MHO T4 SNI G 08/11/2021 - 07:30 12/11/2021 - 18:00 C RS 1098940 Cancelled 07/05/2012 - 15:52
GFD FDR 22 SNI L 08/11/2021 - 07:00 12/11/2021 - 16:00 C RS 1095066 Approved 07/05/2012 - 15:53
HAY T2 SNI G 06/11/2021 - 06:00 06/11/2021 - 18:00 D RS 1098928 Cancelled 07/05/2012 - 15:52
FHL RDF 1 SNI G 04/11/2021 - 07:30 04/11/2021 - 18:00 D RS 1098893 Cancelled 07/05/2012 - 15:52
WKM RTU 1 NNI G 02/11/2021 - 08:00 04/11/2021 - 18:30 D RS 1097696 Approved 07/05/2012 - 15:49
EDG KAW 3 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C RS 1088178 Approved 07/05/2012 - 15:49
EDG OWH 2 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C OPE 1097671 Approved 07/05/2012 - 15:49
KAW T11 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C RS 1085608 Approved 07/05/2012 - 15:49
KAW T12 NNI G 02/11/2021 - 07:30 05/11/2021 - 18:00 C RS 1085609 Approved 07/05/2012 - 15:49
KAW 547 587 627 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C RS 1085598 Approved 07/05/2012 - 15:50
KAW 587 554 637 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C RS 1085592 Approved 07/05/2012 - 15:50
CCT 902 TPI WRO SNI G 02/11/2021 - 07:30 02/11/2021 - 17:30 D RS 1098887 Cancelled 07/05/2012 - 15:52
DRY OTA 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1085158 Approved 07/05/2012 - 15:50
EDG TRK 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1084879 Approved 07/05/2012 - 15:49
TAK T5 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1085159 Approved 07/05/2012 - 15:49
HAY T12 SNI G 01/11/2021 - 07:30 01/11/2021 - 17:30 D RS 1098927 Cancelled 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.