Outage planning results

Last updated: Tue, 19/10/2021 - 12:10
Your current search

Sites: all sites selected

Outages search found 3635 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HEP 33BS K NNI L 27/10/2021 - 13:00 27/10/2021 - 18:00 D RS 1104935 Approved 17/11/2015 - 10:03
HEP 110CBF NNI G 07/03/2022 - 07:00 07/03/2022 - 18:00 D RS 1109218 Approved 07/05/2012 - 15:50
HEP 110CBF NNI G 28/03/2022 - 07:00 28/03/2022 - 18:00 D RS 1109236 Approved 07/05/2012 - 15:50
HEP 110CBF NNI G 10/04/2022 - 07:00 10/04/2022 - 18:00 D RS 1109241 Approved 07/05/2012 - 15:50
HEP 110CBF NNI G 19/04/2022 - 07:00 19/04/2022 - 18:00 D RS 1109248 Approved 07/05/2012 - 15:50
HEP 110CBF NNI G 20/03/2022 - 07:00 20/03/2022 - 18:00 D RS 1109227 Approved 07/05/2012 - 15:50
HEP 110CBF NNI G 01/05/2022 - 07:00 01/05/2022 - 18:00 D RS 1109253 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 19/04/2022 - 07:00 19/04/2022 - 18:00 D RS 1109245 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 01/05/2022 - 07:00 01/05/2022 - 18:00 D RS 1109252 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 10/04/2022 - 07:00 10/04/2022 - 18:00 D RS 1109240 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 28/03/2022 - 07:00 28/03/2022 - 18:00 D RS 1109235 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 20/03/2022 - 07:00 20/03/2022 - 18:00 D RS 1109226 Approved 07/05/2012 - 15:50
HEP 110BZ C NNI G 07/03/2022 - 07:00 07/03/2022 - 18:00 D RS 1109217 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 20/03/2022 - 07:00 20/03/2022 - 18:00 D RS 1109225 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 01/05/2022 - 07:00 01/05/2022 - 18:00 D RS 1109251 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 19/04/2022 - 07:00 19/04/2022 - 18:00 D RS 1109244 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 10/04/2022 - 07:00 10/04/2022 - 18:00 D RS 1109239 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 28/03/2022 - 07:00 28/03/2022 - 18:00 D RS 1109234 Approved 07/05/2012 - 15:50
HEP 110BZ B NNI G 07/03/2022 - 07:00 07/03/2022 - 18:00 D RS 1109216 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 28/03/2022 - 07:00 28/03/2022 - 18:00 D RS 1109233 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 19/04/2022 - 07:00 19/04/2022 - 18:00 D RS 1109243 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 01/05/2022 - 07:00 01/05/2022 - 18:00 D RS 1109250 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 20/03/2022 - 07:00 20/03/2022 - 18:00 D RS 1109224 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 07/03/2022 - 07:00 07/03/2022 - 18:00 D RS 1109215 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 10/04/2022 - 07:00 10/04/2022 - 18:00 D RS 1109238 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.