Outage planning results

Last updated: Thu, 13/08/2020 - 20:10
Your current search

Sites: all sites selected

Outages search found 4041 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TGA FDR 19 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095041 Approved 07/05/2012 - 15:50
TGA FDR 19 NNI L 03/06/2021 - 07:30 03/06/2021 - 18:00 D RS 1085872 Approved 07/05/2012 - 15:50
TGA FDR 20 NNI L 04/06/2021 - 07:30 04/06/2021 - 18:00 D RS 1085873 Approved 07/05/2012 - 15:50
TGA FDR 20 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095042 Approved 07/05/2012 - 15:50
TGA FDR 20 NNI L 16/11/2020 - 06:30 16/11/2020 - 18:30 D RS 1095035 Approved 07/05/2012 - 15:50
TGA FDR 21 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095043 Approved 07/05/2012 - 15:50
TGA FDR 21 NNI L 16/11/2020 - 06:30 16/11/2020 - 18:30 D RS 1095034 Approved 07/05/2012 - 15:50
TGA FDR 21 NNI L 08/06/2021 - 07:30 08/06/2021 - 18:00 D RS 1085874 Approved 07/05/2012 - 15:50
TGA CB 38 NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095037 Approved 07/05/2012 - 15:50
TGA CB 38 NNI L 17/11/2020 - 06:30 19/11/2020 - 18:30 C RS 1095057 Approved 07/05/2012 - 15:50
TGA CB 38 NNI L 20/08/2020 - 17:30 20/08/2020 - 18:00 D PSO 1094749 Approved 07/05/2012 - 15:50
TGA 11BS A NNI L 17/11/2020 - 06:30 19/11/2020 - 18:30 C RS 1095056 Approved 07/05/2012 - 15:50
TGA 11BS B NNI L 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095036 Approved 07/05/2012 - 15:50
KAW 167 VT47 NNI G 03/11/2020 - 07:30 03/11/2020 - 18:30 D RS 1095321 Approved 07/05/2012 - 15:50
PEN CB 798 NNI G 12/10/2020 - 07:00 17/10/2020 - 18:00 C RS 1094127 Approved 07/05/2012 - 15:50
PEN CB 798 NNI G 18/01/2021 - 07:00 22/01/2021 - 19:00 C RS 1094116 Approved 07/05/2012 - 15:50
KPO 77 117 137 NNI G 01/03/2021 - 07:00 01/03/2021 - 18:00 D RS 1085663 Cancelled 07/05/2012 - 15:50
MNG 1087 1107 2338 NNI L 18/01/2021 - 07:30 27/02/2021 - 18:30 C RS 1093607 Approved 07/05/2012 - 15:50
MNG 1087 1107 2338 NNI L 20/03/2021 - 07:00 20/03/2021 - 18:00 D RS 1085680 Approved 07/05/2012 - 15:50
MNG 1107 1087 1047 NNI L 18/01/2021 - 07:30 27/02/2021 - 18:30 C RS 1093608 Approved 07/05/2012 - 15:50
MNG 1047 1054 2368 NNI L 18/01/2021 - 07:30 27/02/2021 - 18:30 C RS 1093606 Approved 07/05/2012 - 15:50
EDG 207 217 237 NNI G 28/10/2020 - 08:30 28/10/2020 - 16:00 D RS 1092723 Approved 07/05/2012 - 15:50
EDG 207 217 237 NNI G 27/08/2020 - 07:30 27/08/2020 - 18:30 D RS 1093357 Approved 07/05/2012 - 15:50
HEN 467 514 524 NNI G 12/04/2021 - 07:30 16/04/2021 - 18:30 C RS 1093693 Approved 07/05/2012 - 15:50
EDG 437 447 467 NNI G 08/10/2020 - 07:30 09/10/2020 - 18:30 C RS 1086062 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.