Outage planning results

Last updated: Mon, 06/07/2020 - 17:40
Your current search

Sites: all sites selected

Outages search found 4093 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ALB 220BZ NNI G 27/11/2020 - 07:30 27/11/2020 - 18:00 D RS 1085370 Cancelled 07/05/2012 - 15:50
ALB 220BZ NNI G 30/07/2020 - 07:30 31/07/2020 - 18:00 D RS 1085372 Approved 07/05/2012 - 15:50
BRB MDN 1 PROT1 NNI G 12/10/2020 - 08:00 12/10/2020 - 10:00 D RS 1094111 Approved 07/05/2012 - 15:50
BRB MDN 1 PROT1 NNI G 08/12/2020 - 08:00 08/12/2020 - 10:00 D RS 1094501 Approved 07/05/2012 - 15:50
ATI 47 157 147 NNI G 15/12/2020 - 09:00 15/12/2020 - 14:00 D RS 1092720 Approved 07/05/2012 - 15:50
BRB MDN 1 PROT2 NNI G 08/12/2020 - 10:00 08/12/2020 - 12:00 D RS 1094502 Approved 07/05/2012 - 15:50
BRB MDN 1 PROT2 NNI G 12/10/2020 - 10:00 12/10/2020 - 12:00 D RS 1094112 Approved 07/05/2012 - 15:50
WAI 11BS NNI L 15/11/2020 - 07:30 15/11/2020 - 18:00 D RS 1085910 Approved 07/05/2012 - 15:50
EDG 217 207 324 NNI G 09/02/2021 - 07:30 09/02/2021 - 18:00 D RS 1085455 Approved 07/05/2012 - 15:50
EDG CB 222 NNI G 28/10/2020 - 08:30 28/10/2020 - 16:00 D RS 1092724 Approved 07/05/2012 - 15:50
EDG CB 222 NNI G 27/08/2020 - 07:30 27/08/2020 - 18:30 D RS 1093356 Approved 07/05/2012 - 15:50
OHK CB 102 NNI G 28/09/2020 - 07:30 29/09/2020 - 18:30 D RS 1086084 Approved 07/05/2012 - 15:50
HLY TWH 1 NNI G 25/01/2021 - 07:30 29/01/2021 - 18:30 C RS 1088920 Approved 07/05/2012 - 15:50
TWH RTU 1 NNI G 16/12/2020 - 08:00 16/12/2020 - 18:00 D RS 1089728 Approved 07/05/2012 - 15:50
TWH RTU 1 NNI G 25/11/2020 - 08:00 25/11/2020 - 18:00 D RS 1089726 Approved 07/05/2012 - 15:50
TWH T1 NNI G 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1088297 Approved 07/05/2012 - 15:50
TWH T2 NNI G 12/10/2020 - 07:30 13/10/2020 - 18:00 D RS 1088298 Approved 07/05/2012 - 15:50
TWH CB 2808 NNI L 12/10/2020 - 07:30 13/10/2020 - 18:00 D RS 1088005 Approved 07/05/2012 - 15:50
TWH CB 2808 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1088003 Approved 07/05/2012 - 15:50
TWH 33BS B NNI L 12/10/2020 - 07:30 13/10/2020 - 18:00 D RS 1088004 Approved 07/05/2012 - 15:50
TWH 33BS B NNI L 07/12/2020 - 07:00 11/12/2020 - 18:00 C RS 1089727 Approved 07/05/2012 - 15:50
TWH 33BS A NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1088002 Approved 07/05/2012 - 15:50
TWH 33BS A NNI L 30/11/2020 - 07:00 04/12/2020 - 18:00 C RS 1089725 Approved 07/05/2012 - 15:50
TWH FDR 2742 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1085903 Approved 07/05/2012 - 15:50
TWH FDR 2762 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1085904 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.