Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB OTA 1 NNI G 10/06/2019 - 07:30 15/06/2019 - 18:30 C RS 1077253 Approved 07/05/2012 - 15:49
BOB OTA 1 NNI G 21/03/2019 - 07:30 21/03/2019 - 18:30 D RS 1078116 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 25/03/2019 - 07:30 30/03/2019 - 18:30 C RS 1072680 Cancelled 07/05/2012 - 15:49
BOB OTA 2 NNI G 24/06/2019 - 07:00 29/06/2019 - 18:30 C RS 1077262 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 20/05/2019 - 10:00 20/05/2019 - 14:00 D SCA 1071844 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 26/06/2019 - 13:00 26/06/2019 - 18:30 D SCA 1077265 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 12/06/2019 - 13:00 12/06/2019 - 18:30 D SCA 1077257 Approved 07/05/2012 - 15:49
BOB T2 NNI G 20/05/2019 - 07:00 21/05/2019 - 17:00 D RS 1071824 Approved 07/05/2012 - 15:49
BPD STU GXP TIE SI G 05/05/2019 - 09:00 05/05/2019 - 11:00 D OTH 1078022 Approved 01/11/2013 - 08:35
BPD STU GXP TIE SI G 03/05/2019 - 17:30 03/05/2019 - 18:30 D OTH 1078021 Approved 01/11/2013 - 08:35
BPD STU GXP TIE SI G 28/04/2019 - 10:00 28/04/2019 - 12:00 D OTH 1078019 Approved 01/11/2013 - 08:35
BPD STU GXP TIE SI G 15/04/2019 - 15:00 15/04/2019 - 19:00 D OTH 1078018 Approved 01/11/2013 - 08:35
BPD STU GXP TIE SI G 15/04/2019 - 06:30 15/04/2019 - 07:00 D OTH 1078017 Approved 01/11/2013 - 08:35
BPD STU GXP TIE SI G 14/04/2019 - 10:00 14/04/2019 - 14:00 D OTH 1078016 Approved 01/11/2013 - 08:35
BPD STU GXP TIE SI G 29/04/2019 - 06:00 29/04/2019 - 06:30 D OTH 1078020 Approved 01/11/2013 - 08:35
BPE 110BZ SNI G 17/07/2019 - 07:30 01/12/2019 - 18:00 D RS 1070644 Cancelled 07/05/2012 - 15:53
BPE 110CBF SNI G 17/07/2019 - 07:30 02/12/2019 - 18:00 D RS 1070645 Cancelled 07/05/2012 - 15:53
BPE 220BS B SNI G 28/11/2019 - 07:30 03/12/2019 - 18:00 D RS 1070646 Cancelled 07/05/2012 - 15:52
BPE 220BS CHANGE SNI G 29/03/2019 - 06:30 29/03/2019 - 07:00 D PSO 1077557 Approved 07/05/2012 - 15:53
BPE 220BS CHANGE SNI G 28/03/2019 - 06:30 28/03/2019 - 07:00 D PSO 1077556 Approved 07/05/2012 - 15:53
BPE 220BS CHANGE SNI G 28/03/2019 - 18:00 28/03/2019 - 18:30 D PSO 1077560 Approved 07/05/2012 - 15:53
BPE 220BS CHANGE SNI G 03/04/2019 - 07:00 03/04/2019 - 07:30 D PSO 1077964 Approved 07/05/2012 - 15:53
BPE 220BS CHANGE SNI G 29/03/2019 - 18:00 29/03/2019 - 18:30 D PSO 1077561 Approved 07/05/2012 - 15:53
BPE 220BS CHANGE SNI G 27/03/2019 - 06:30 27/03/2019 - 07:00 D PSO 1077555 Approved 07/05/2012 - 15:53
BPE 220BS CHANGE SNI G 03/04/2019 - 18:30 03/04/2019 - 19:00 D PSO 1077965 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.