Outage planning results

Last updated: Mon, 16/09/2019 - 07:40
Your current search

Sites: all sites selected

Outages search found 4339 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
OTA ROS 2 NNI G 25/11/2019 - 07:30 27/11/2019 - 18:00 C RS 1081615 Approved 07/05/2012 - 15:49
HLY OTA 2 NNI G 29/01/2020 - 07:30 30/01/2020 - 18:30 C RS 1072048 Approved 07/05/2012 - 15:49
OTA ROS 2 NNI G 06/05/2019 - 07:30 30/10/2019 - 18:30 C RS 1077168 Released 07/05/2012 - 15:49
HIN RTU 1 NNI G 17/10/2019 - 08:00 18/10/2019 - 16:00 C RS 1081903 Approved 07/05/2012 - 15:49
KPU 367 VT10 NNI G 20/04/2020 - 07:30 21/04/2020 - 18:30 C RS 1083109 Approved 07/05/2012 - 15:49
KPU 367 VT10 NNI G 14/10/2019 - 07:30 18/10/2019 - 18:00 C RS 1070151 Approved 07/05/2012 - 15:49
MNG ROS 2 NNI G 14/10/2019 - 07:30 18/10/2019 - 18:30 C RS 1072220 Approved 07/05/2012 - 15:49
ROS T4 NNI G 15/10/2019 - 07:00 17/10/2019 - 18:00 C RS 1080327 Approved 07/05/2012 - 15:49
TAK T5 NNI G 18/02/2020 - 07:00 20/02/2020 - 18:00 C RS 1072044 Approved 07/05/2012 - 15:49
PEN 777 807 NNI G 23/09/2019 - 07:00 04/10/2019 - 16:00 C RS 1078270 Cancelled 07/05/2012 - 15:50
TAK T5 NNI G 18/11/2019 - 07:30 22/11/2019 - 18:30 C RS 1070156 Approved 07/05/2012 - 15:49
ALB 607 627 707 NNI G 02/03/2020 - 07:30 06/03/2020 - 18:30 C RS 1073291 Approved 07/05/2012 - 15:50
TAK T8 NNI G 29/01/2020 - 07:30 30/01/2020 - 18:30 C RS 1072049 Approved 07/05/2012 - 15:49
ALB 327 VT3 NNI G 30/03/2020 - 07:30 04/04/2020 - 18:30 C RS 1080570 Approved 07/05/2012 - 15:50
TGA T2 NNI G 28/05/2020 - 07:30 29/05/2020 - 18:30 C RS 1070531 Approved 07/05/2012 - 15:49
HEN 467 514 524 NNI G 09/12/2019 - 07:30 13/12/2019 - 18:30 C RS 1073337 Approved 07/05/2012 - 15:50
WKM CB 228 NNI G 21/05/2020 - 07:30 22/05/2020 - 17:00 C RS 1070073 Approved 07/05/2012 - 15:50
WKM CB 248 NNI G 21/01/2020 - 07:30 22/01/2020 - 18:30 C RS 1070265 Approved 07/05/2012 - 15:50
WKM 220BS A NNI G 24/02/2020 - 07:30 25/02/2020 - 18:30 C RS 1070252 Approved 07/05/2012 - 15:50
WKM 220BS B NNI G 19/05/2020 - 07:30 20/05/2020 - 17:00 C RS 1070169 Approved 07/05/2012 - 15:50
WKO T2 NNI G 04/05/2020 - 07:30 07/05/2020 - 18:30 C RS 1070620 Approved 07/05/2012 - 15:49
WKO T2 NNI G 09/03/2020 - 07:30 09/04/2020 - 18:30 C RS 1070618 Approved 07/05/2012 - 15:49
OTA T3 NNI G 23/06/2020 - 07:30 26/06/2020 - 18:30 C RS 1070449 Approved 07/05/2012 - 15:49
APS OTI 1 SI G 02/10/2019 - 07:00 04/10/2019 - 18:30 C RS 1081800 Approved 07/05/2012 - 15:51
APS OTI 1 SI G 02/03/2020 - 05:30 06/03/2020 - 18:30 C RS 1069827 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.