This consultation closed on Friday 2 October 2026.
The System Operator is proposing updates to the Ancillary Services Procurement Plan (ASPP) to implement the new Emergency Reserve ancillary service.
Background information
The ASPP sets out the commercial and technical requirements for ancillary service providers to meet. The current version does so for instantaneous reserves, frequency keeping, black start, voltage support and over-frequency reserves.
In March the Electricity Authority decided to introduce a new ancillary service - Emergency Reserve - to strengthen power system reliability by enabling paid demand-response during acute system stress events. Emergency Reserve will be the last tool available to the System Operator before instructed involuntary demand management. The System Operator is now working to implement that decision in our operational tools and processes, and the commercial arrangements with providers that will be governed by the ASPP.
Feedback received during this consultation informed the final amendment proposal that Transpower, as System Operator, has submitted to the Authority. A new ASPP will take effect once it has been approved by the Authority.
Consultation process
The consultation period was three weeks commencing 7 September 2026. Submissions were due by 5pm on 25 September 2026. This was followed by a one week period for cross-submissions. Cross-submissions were due by 5pm on 2 October 2026.
Consultation Documents
Consultation Responses
| Blackcurrent | View |
| ENA | View |
| Enel X Part 1 | View |
| Enel X Part 2 | View |
| Haast Energy | View |
| Lastmyle | View |
| Mercury | View |
| Simply Energy | View |
| Unison Networks | View |
Cross-Submissions
We received no cross-submissions.
Our Response
We completed consultation earlier this year on a draft proposal to amend the ASPP to incorporate Emergency Reserve. Following our review of submissions, we have decided to:
- Add an option for the System Operator to specify a maximum event duration (noting this is unlikely to be used in year 1).
- Amend the definition of ‘emergency reserve equipment’ to clarify how it applies to aggregated assets.
- Add provisions for a maximum rate of change in power consumed/generated to be specified at both activation and restoration.
- Make changes to improve clarity on outages for aggregated assets, baselining where past data is not required, and what should happen if a self-certification shows that the ancillary services agent cannot meet the performance requirements.