The connections process manages how new generation and load connect to the grid, enabling renewable investment, electrification, and security of supply.
From 2019, enquiries for connections to the grid increased sharply, putting ongoing pressure on our processes and resources.
In response, we introduced a Connections Management Framework (CMF) in 2022, shifting from a first-in, first-served approach to a more staged, readiness-based model.
Read our current Connections Management Framework (4.0).
Reviews of the CMF
Since 2022, we have regularly reviewed the CMF and made improvements to the process, significantly reducing the time taken to deliver connections. We have consulted on the proposed changes before implementing them each time. The past versions of the CMF are provided in links at the bottom of this page, along with analysis documents outlining the key changes from version to version. These updates have meant our process has kept pace with the changing dynamics of the connection enquiry pipeline and further streamlined our internal approach.
In 2026, the Electricity Authority commissioned an independent review of the CMF, which was undertaken by MartinJenkins. The review found that overall, Transpower’s connections process is fit for purpose and broadly consistent with international peers. While customers generally considered the process effective, the review identified opportunities to improve predictability, communication, and the visibility of performance information. We are responding to the recommendations made in that report, which also noted our commitment to continuous improvement.
The most recent update - CMF 4.0, Nov 2026
Earlier in 2026, we indicated that we would extend the CMF to include grid connections for new load and other non-generation projects. This is now in place, with CMF 4.0 replacing the existing CMF 3.0 version.
The new update includes additional information requirements for large load applications, designed to complement the new large load commissioning guideline published by the System Operator.
To help manage a smooth transition to the new settings, we briefly suspended acceptance of requests on Tuesday 17 November 2026 to progress grid connections for new load and other non-generation investigation projects to allow potential applicants to familiarise themselves with the new requirements.
From Monday 23 November 2026 we resume accepting new applications, now under the revised CMF process – this pause does not affect pre-existing requests for investigations or projects already underway.
This change does not affect applications for generation and energy storage connections, although minor changes have been made to the application form and guidance notes – and all applications must use this new form.
If you have any questions, please don’t hesitate to contact us at [email protected].
Connection Management Framework (4.0)
What's changed from version 3.0 to 4.0
A record of previous CMF documents