Resources
Displaying 51 - 60 of 109
Last updated: 31 Jul 2024
Appendix B Study Methodology.pdf
… scenarios as the objective of the analysis is to test the transmission system’s limitations. These are during winter … the New Zealand grid is invaluable, and guidance for this report was solicited from those most familiar with these … the forecast developed for Transpower’s 2023 Transmission Planning Report (TPR) is used in these studies. However, it …
Last updated: 14 Nov 2023
2024 SOSA - Reference Case and Sensitivities Consultation.pdf
… energy margins assess the adequacy of generation and HVDC transmission capacity to meet expected electricity demand … Document https://www.transpower.co.nz/system-operator/planning-future/security-supply-annual-assessment … mazonaws.com/public/bulk-upload/documents/Market%20insight%20report%20-%20Winter%20Review%20-%2011%20Nov%202022.pdf …
Last updated: 05 Aug 2025
SO Industry Forum 5 August 2025
… assessments highlight some upcoming tighter periods due to transmission outages reducing the post- contingent voltage … stem-operator/notices-and-reporting/market-operations-weekly-report/energy-security-outlook … stem-operator/notices-and-reporting/market-operations-weekly-report/energy-security-outlook TRANSPOWER.CO.NZ Any …
Last updated: 12 Nov 2024
Security of Supply Outlook_30Sep2024.pdf
… and work to improve clarity of the Electricity Risk Curves reporting in relation to contingent storage and Watch … https://www.transpower.co.nz/system-operator/planning-future/security-supply-annual-assessment TRANSPOWER … Transpower as the grid owner cancelled and delayed some transmission outages to release affected generation. The New …
Last updated: 15 Jul 2024
Quarterly System performance information - April to June 2024.pdf
… © Transpower New Zealand Limited. All rights reserved. ii Report Purpose To provide information on ancillary service … 09:00 A grid emergency was declared to remove South Island transmission circuits from service to assist with managing … 10:45 A grid emergency was declared to remove North Island transmission circuits from service to assist with managing …
Last updated: 22 Dec 2022
Part D NI Backbone.pdf
… 220 kV grid backbone 2. SYSTEM CONDITIONS Transpower’s 2022 Transmission Planning Report (TPR) identified five system conditions which …
Last updated: 16 Dec 2022
Part G Resources.pdf
… of the committed project test set out in Part B of this report. Contingency Plan A plan that identifies power system … Code. Contingent events include the loss of any single transmission circuit or generating unit, but do not include … AOPO Asset Owner Performance Obligations APR Annual Planning Report AUFLS Automatic Under-Frequency Load …
Last updated: 29 Apr 2025
SO Industry Forum 29 April 2025
… additional capacity available. • Grid Owner to increase transmission offers where generation may be constrained. Low … to provide more generation. • Grid Owner to increase transmission offers where generation may be constrained. • … preparing our draft Security of Supply Assessment (SOSA) report for consultation which is anticipated to open later …
Last updated: 13 Dec 2024
Low_Residual_Situation_Review_Consultation
… but uncleared generation, ▪ request Transpower as the transmission grid owner to increase transmission offers or require them to reconfigure the grid … https://www.transpower.co.nz/system-operator/notices-and-reporting TRANSPOWER NZ | SYSTEM OPERATOR CONSULATION PAPER …
Last updated: 24 Jul 2025
N - 1 Thermal and Voltage Study_Minor Update 2025 June
… and voltage stability issues. For these contingencies, the report notes both future grid projects that will resolve the … troughs In the previous SSF, assessments indicated several transmission circuits would need to be removed from service … of new reactors and STATCOMs, the need to switch off transmission circuits during light load has decreased. …