Resources
Displaying 111 - 120 of 202
Last updated: 10 Oct 2018
BRK-SFD Long List Consultation.pdf
… Value of expected unserved energy The Value of Lost Load (VoLL, also known as Value of Expected Unserved Energy) is … Schedule 12.2 of the code Question 10: Do you consider this VoLL ($26,200/MWh) appropriate for valuing unserved energy? … for this investigation? 10. Do you consider this VoLL ($26,200/MWh) appropriate for valuing unserved energy? …
BRK-SFD Long List Consultation.pdf
(PDF 1.24 MB)
Last updated: 15 Dec 2020
MEUG submission on TPM Options Consultation, Part B and Part C.pdf
… not be based on a single or small number of generalised VoLL estimates. Transpower proposes to depart from the …
Last updated: 27 Sep 2019
2017 ITP Services Report.pdf
… them against our estimated Value of Lost Load (VoLL). Generally the RCP 2 targets determined using these … of this review includes a review of value of lost load (VoLL) which is a key input into the categorisation review. … by customer category GP1 Categorisation to be aligned with VoLL Average duration of unplanned interruptions by customer …
2017 ITP Services Report.pdf
(PDF 4.12 MB)
Last updated: 26 Sep 2017
2017 ITP Services Report.pdf
… them against our estimated Value of Lost Load (VoLL). Generally the RCP 2 targets determined using these … of this review includes a review of value of lost load (VoLL) which is a key input into the categorisation review. … by customer category GP1 Categorisation to be aligned with VoLL Average duration of unplanned interruptions by customer …
2017 ITP Services Report.pdf
(PDF 4.12 MB)
Last updated: 07 Dec 2016
TP_Sub_Extended_Reserves_Selection_Methodology_29Nov2016.pdf
… set out in the data specification? We assume this very high VOLL has some basis. We agree with tighter specification for …
TP_Sub_Extended_Reserves_Selection_Methodology_29Nov2016.pdf
(PDF 550.41 KB)
Last updated: 15 Dec 2020
ENA submission on TPM Options Consultation, Part B and Part C.pdf
… number of important input assumptions (eg: the $ value of VoLL or the operational $ cost of generators) that are …
Last updated: 12 Nov 2014
Arapuni Grid Reconfiguration August 2011.pdf
… ‘south’ bus generation, 0.5 hours to restore connection, a VOLL of $20000/MWh, the energy not served costs are 45% …
Arapuni Grid Reconfiguration August 2011.pdf
(PDF 240.56 KB)
Last updated: 08 Nov 2021
Grid Outputs Report 2021.pdf
… with contingency planning. We use Value of Lost Load (VoLL) as a common input across frameworks, enabling us to … and gauge end users’ expectations. Additionally, we use VoLL to support network enhancement and development …
Grid Outputs Report 2021.pdf
(PDF 828.31 KB)
Last updated: 01 Oct 2019
Bunnythorpe-Wilton Preferred Option Summary of Submissions.pdf
… have been used. For estimating reliability benefits VoLL has been applied to the 2018 TPR demand scenarios. For …
Bunnythorpe-Wilton Preferred Option Summary of Submissions.pdf
(PDF 850.45 KB)
Last updated: 02 Oct 2018
Bunnythorpe-Wilton Preferred Option Summary of Submissions.pdf
… have been used. For estimating reliability benefits VoLL has been applied to the 2018 TPR demand scenarios. For …
Bunnythorpe-Wilton Preferred Option Summary of Submissions.pdf
(PDF 850.45 KB)