Resources
Displaying 41 - 50 of 230
Last updated: 03 Jul 2023
SO full report - Hawkes Bay loss of supply.pdf
… 13 Table 3 - Estimated VoLL (08:00 14/02/23 - 16:30 10/03/23) … time to restore service, the estimated value of lost load (VoLL4) for the duration of the grid emergency (08:00 14/02/23 - 16:30 10/03/23) is significant. VoLL was determined by comparing the load successfully …
Last updated: 19 Dec 2018
BOB-OTA Long List.pdf
… Value of expected unserved energy The Value of Lost Load (VoLL, also known as Value of Expected Unserved Energy) is … value of $26,200/MWh. More recently we have completed a VoLL study which looked at appropriate VoLL values for each GXP, reflecting the …
Last updated: 27 Sep 2019
Grid Outputs Report 2018.pdf
… the results of our recently completed Value of Lost Load (VoLL) study, and spent time considering how to group Points … • Retained grid performance measures GP1 and GP2, applied VoLL, and refreshed the PoS categories • Discontinued GP3 • … for event management with contingency planning. We use VoLL as a common input across frameworks. It enables us to …
Last updated: 28 Nov 2018
Grid Outputs Report 2018 - FINAL.pdf
… the results of our recently completed Value of Lost Load (VoLL) study, and spent time considering how to group Points … • Retained grid performance measures GP1 and GP2, applied VoLL, and refreshed the PoS categories • Discontinued GP3 • … for event management with contingency planning. We use VoLL as a common input across frameworks. It enables us to …
Last updated: 01 Oct 2019
MEUG to TPNZ, Bunnythorpe to Wilton line reconductoring, 19-Oct-16.pdf
… to be used in Investment Tests. 8. Do you consider this VoLL ($25,300/MWh) appropriate for valuing unserved energy? … this Investment Test assumption. 9. Do you consider this VoLL appropriate for valuing lost load for your business? If, not, what alternative VoLL would you recommend and what evidence are you able to …
Last updated: 01 Mar 2018
MEUG to TPNZ, Bunnythorpe to Wilton line reconductoring, 19-Oct-16.pdf
… to be used in Investment Tests. 8. Do you consider this VoLL ($25,300/MWh) appropriate for valuing unserved energy? … this Investment Test assumption. 9. Do you consider this VoLL appropriate for valuing lost load for your business? If, not, what alternative VoLL would you recommend and what evidence are you able to …
Last updated: 08 Oct 2018
Focus Group session slides 21 June 18.pdf
… • results of our recently completed Value of Lost Load (VoLL) study • for measures AP2 and AP3, identifying which … the amount of load being served at a POS multiplied by the VoLL at that POS, and is the expected dollar cost of an … are broken down broadly into the following types: Step 2: A VoLL for each type of consumer is established. Step 3: The …
Last updated: 11 May 2026
Vector submission WUNI2
… is dispatched at peak and a $600/MWh value of lost load (VoLL). Without contractually procuring the capacity, there … the load cannot be reduced which will in turn push up the VoLL that will need to be used in the calculation. Yours …
Last updated: 11 May 2026
Vector submission.pdf
… is dispatched at peak and a $600/MWh value of lost load (VoLL). Without contractually procuring the capacity, there … the load cannot be reduced which will in turn push up the VoLL that will need to be used in the calculation. Yours …
Last updated: 09 Aug 2017
Busbar Classification July 17 - Summary of Submissions.pdf
… and ROS 22kV bus. 5 WEL Networks queried whether the VOLL used in the assessment should be per customer category. … we do not believe it is appropriate to use specific VOLL per customer category. To do so would require a level …