Resources
Displaying 281 - 290 of 1234
Last updated: 16 Dec 2022
PBA Independent Review of HVDC Power Reduction Event 7 October 2022 - Final Report.pdf
… Approved By: Tony Armstrong – Director, PBA Consulting Report Number: JC-001-105 Final Report 16 November 2022 … responded by cancelling a number of planned generation and transmission outages so as to improve the resilience of the … Electronics System Operator Operations Manager Operations Planning Manager 3. Background to HVDC Operation 3.1. …
Last updated: 15 Apr 2024
Health Safety and Wellbeing Board Report March 2024.pdf
… TP.HSW 01.13b Health, safety and wellbeing performance report 3 Actions Closed 1 Actions Raised Monitor FY 23/24 … Wednesday, 31 July 2024 APPR New action raised to assess transmission standard steel pole ‘winching lug’ viability … site specific run engineering specification. Following the ‘transmission lines best practice guide’, no one was located …
Health Safety and Wellbeing Board Report March 2024.pdf
(PDF 3.65 MB)
Last updated: 13 Sep 2024
Health Safety Wellbeing Board Report August 2024.pdf
… Corrective Actions Status Workplan Delivery Assurance l Reporting l <6 Target Controls Checked 755 Worksafe … activities were pivoted and focused on People (competency), Planning for the work (including procedures) and Supervision … site specific run engineering specification. Following the ‘transmission lines best practice guide’, no one was located …
Health Safety Wellbeing Board Report August 2024.pdf
(PDF 3.25 MB)
Last updated: 29 Jun 2022
2022 SOSA - Final Report - Final Version.pdf
… 44 4.2.6 Inter-Island Transmission Assumptions … demand forecast aligned with transmission and strategic planning (e.g. Whakamana i Te Mauri Hiko), the Electricity … and demand, as highlighted in our Weekly Market Movements report (Market Operations - Weekly Market Movements - 28 …
2022 SOSA - Final Report - Final Version.pdf
(PDF 4.37 MB)
Last updated: 02 Aug 2021
Procurement Plan 2022 - Marked Up.pdf
… 8.43(f) of the Code) ................... 14 System operator reporting to the Authority (clause 8.43(g) of the Code) … and dispatching ancillary services to assist it in planning to comply and complying with its dispatch … generation output that supports the initial charging of transmission circuits and assets, and the progressive …
Procurement Plan 2022 - Marked Up.pdf
(PDF 608.25 KB)
Last updated: 15 Dec 2020
Trustpower submission on TPM Options Consultation - Attachment 2 - JC 2020 Report - Example_UpperWaitaki_FINAL.pdf
… this worked example 8 Dec 2020 John Culy JC2JC2Introduction Report to TrustPower - 8 December 2020 2 o TrustPower … for the current Clutha Upper Waitaki Lines Project. o This transmission project is relatively simple and straight … schemes that is likely with Tiwai exit and without the transmission investment. The major uncertainty relates to …
Last updated: 19 Oct 2023
Health Safety & Wellbeing Board Report September 2023.pdf
… TP.HSW 01.13b Health, safety and wellbeing performance report 2.46 176 0 Actions Raised 0 Actions Closed 22973 … TP.HSW 01.13b Health, safety and wellbeing performance report September 2023 Oct 2022 Nov 2022 Dec 2022 Jan 2023 … site specific run engineering specification. Following the ‘transmission lines best practice guide’, no one was located …
Last updated: 27 Feb 2017
TP_TPM_Supplementary_Appendix_B_Axiom_Report_24Feb2017.pdf
… Economic Review of Transmission Pricing Supplementary Consultation Paper A Report for Transpower February 2017 Project Team Hayden … building in the near-term, e.g., to find a site, obtain planning approvals, arrange financing, undertake …
TP_TPM_Supplementary_Appendix_B_Axiom_Report_24Feb2017.pdf
(PDF 873.62 KB)
Last updated: 10 Jun 2025
FINAL Ancillary Services Procurement Plan Review Proposal
… services contracts by technical staff due to additional reporting and testing requirements (particularly to meet the … We would expect that any load that has signed up to a non- transmission solution (NTS), or EDB Demand Response … We would expect that any load that has signed up to a non-transmission solution (NTS), or Demand response programme, …
Last updated: 04 Nov 2022
2022 SOSA - Final Report - (Revised) Final Version.pdf
… to 2024. It is now consistent with the remainder of the report. IMPORTANT Disclaimer The information in this … 45 4.2.6 Inter-Island Transmission Assumptions … demand forecast aligned with transmission and strategic planning (e.g. Whakamana i Te Mauri Hiko), the Electricity …
2022 SOSA - Final Report - (Revised) Final Version.pdf
(PDF 4.63 MB)