Last updated: 09 Dec 2025
What are we doing?
On February 14, 2023, Cyclone Gabrielle caused widespread damage across Hawke’s Bay, destroying hundreds of homes and causing power outages. Most of Hawke’s Bay’s electricity is provided via interconnection at our Redclyffe grid exit point. Redclyffe and Whirinaki substations were both flooded and the flood waters at Redclyffe triggered power outages at Redclyffe, Fernhill, Tuai and Whakatu.
This natural disaster caused the greatest loss of power supply the region has experienced.
Transpower and Unison, the local electricity distributor, have reviewed the need for resilient infrastructure so that people and business in Hawke’s Bay can have a greater level of assurance that another major flood event will not cause a similar power outage.
Our focus is now on rebuilding the substation with increased resiliency.
We proposed this investment to the Commerce Commission in June 2025. We have since received confirmation from the Commission in December 2025 that it supports our planned investment, and you can read our media release here.
All our application documents to the Commerce Commission can be found here.
Following the Commission's consultation on this investment, we expect work to start on the rebuild in October 2026.
Timeline and updates
What has happened so far?
- The 110 kV switchyard has had interim upgrades performed to make the equipment there more resilient to flooding.
- We have installed a new temporary control room above the flood level to ensure that the most critical control equipment is flood resilient.
- A new 220 kV/110 kV interconnecting transformer has been installed. This additional larger capacity transformer is able to supply more electricity into the area, and will meet 1 in 450-year flood protection standards.
- The Commerce Commission has approved our planned investment and will now consult on it. All things going well, we expect work to begin in October 2026 and be completed by December 2027, with no expected impact to local electricity supply.
Consultation on Major Capex Proposal
Transpower has concluded consultation on delivering another level of resilience at Redclyffe Substation in the Hawke’s Bay, which was badly damaged two years ago during Cyclone Gabrielle. This consultation ran from 11 February through to 11 March 2025. Here is the document summarising the submissions we received.
Please see the submissions we received from the following organisations -
These were the consultation documents -
- Summary document
- Redclyffe 220 kV Switchyard Resilience - Shortlist Consultation
- Redclyffe 220 kV Switchyard Resilience - Attachment 1 - Options analysis
- Redclyffe 220 kV Switchyard Resilience - Attachment 2 - Benefits modelling
More information
You can sign up to receive email updates as the work progresses. Click here to get on our mailing list.
Media releases
Investment to strengthen Hawke’s Bay’s infrastructure approved - 9 December, 2025
Hawke's Bay and Tairāwhiti electricity supply given boost - 18 September, 2025
Transpower proposes further investment in power supply for Hawke’s Bay - 12 June, 2025
Transpower consults on Redclyffe substation rebuild - 11 February, 2025
Transpower to consult on rebuilding Redclyffe substation on existing site - 9 May, 2024
Transpower completes further work to improve electricity supply security in cyclone-affected regions - 31 March, 2023
Transpower completes partial restoration of damaged Redclyffe substation - 13 March, 2023
Transpower completes bypass of Redclyffe substation - 17 February, 2023
Transpower continues to work with lines companies to restore power in the Hawke's Bay and Tairāwhiti regions - 16 February, 2023