Overview
For seeking regulatory approval to undertake major capital projects, Transpower follows a 3-stage process:
- Setting out the need for investment and long listing of possible options
- Shortlisting a number of options to take forward for further investigation
- Selecting a preferred option and proposing it to the Commerce Commission.
Our Western Bay of Plenty Programme first started by seeking feedback about our thinking, assumptions, and possible early options for upgrades on the high-voltage electricity transmission network for this region.
Setting out the need for investment and long-listing consultation
What did we consult on?
In this consultation, we set out a 'long-list' of development options that may contribute to meeting these needs. We sought your feedback about these possible solutions.
We recognise there may be non-transmission options that could defer the need for upgrades to our networks, so we also requested information on any such alternatives.
As well as these matters, we also consulted on the thinking that lies behind this work - the need for investment, the electricity demand and generation scenarios on which our analysis is based, and key assumptions we will make.
Consultation documents
Our consultation information included an Overview document and five Attachment documents, each of which focused on a specific aspect of our consultation.
Throughout the consultation documents, we included questions for consideration and response in submissions. These were intended to help respondent, who did not have to answer any or all of these questions, and were welcome to raise other issues relevant to our project. We also provided a template document for responses to these questions.
- WBoP Long-list consultation Overview
- WBoP Long-list consultation Attachment 1 - Need for investment, Regulatory process for approval of investment
- WBoP Long-list consultation Attachment 2 - Long-list of options
- WBoP Long-list consultation Attachment 3 - Information for proponents of non-transmission solutions
- WBoP Long-list consultation Attachment 4 - Scenarios
- WBoP Long-list consultation Attachment 5 - Investment Test parameters
- Question and response document
- Zip file of all documents
Responses to our consultation
We sought and welcomed feedback on our consultation through written submissions. The submission period was from 17 July to 13 September 2023. We extended this period for a few days to those submitters who requested additional time to provide their submissions.
The submissions we received are provided below.
- WBoP long-list submission by ElementIMF
- WBoP long-list submission by Powerco
- WBoP long-list submission by Priority One
- WBoP long-list submission by solarZero
- WBoP long-list submission by Tauranga City Council
- WBoP long-list submission by Western Bay of Plenty District Council
- All WBoP long-list submissions (zip file)
We also provided a summary of these consultation submissions and our responses to the matters raised by submitters.
Short-listing Consultation
Having received feedback to test our assumptions, we then went back to stakeholders with a number of different shortlisted options.
Public consultation was open until 10 September 2024 on the short-list of preferred options.
Our consultation information included an overview document and six attachment documents, each of which focused on a specific aspect of our consultation.
Here are the documents -
- Short List Consultation
- Overview of need - attachment 1
- Shortlist of development - attachment 2
- Scenarios - attachment 3
- Options analysis - attachment 4
- Stakeholder consultation - attachment 5
- Benefits modelling - attachment 6
Consultation responses
See the WBoP - Shortlist Summary of submissions for a summary of the key points raised and Transpower's responses. Individual submissions on the short list options are published below.
- Element IMF Ltd response to Transpower
- FlexAble Ltd response to Transpower
- GeoExchange NZ response to Transpower
- Meridian response to Transpower
- Port of Tauranga response to Transpower
- Powerco response to Transpower
- SmartGrowth response to Transpower
- SolarZero response to Transpower
- Tauranga City Council response to Transpower
- Vector response to Transpower
- Western Bay of Plenty District Council response to Transpower
- Xatech International Pty Ltd response to Transpower
Application to the Commerce Commission
Following our short-listing, we took our preferred development path to the Commerce Commission for approval - their approval allows us to recapture the costs of the project against our balance sheet.
Main proposal document
Supporting documents
WBoP - Attachment 1 - Compliance Requirements
WBoP - Attachment 2 - Overview of need
WBoP - Attachment 3 - Demand and generation scenarios
WBoP - Attachment 4 - Short list of development plans
WBoP - Attachment 5 - Options analysis
WBoP - Attachment 7 - Stakeholder consultation
WBoP - Attachment 8 - Benefits of modelling
WBoP - Attachment 9 - Approach to NTS
WBoP - Attachment 10 - Indicative starting allocations and BBCs
WBoP - Attachment 11 - CEO certification